Energy Projects Near You

Dersalloch (69 MW wind farm)

Dersalloch is a 69 MW wind farm project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 August 2016; the record was last updated on 12 December 2016. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

69 MWwind farm
operationalstatus in REPD
12 December 2016record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
29 July 2005Application submitted
23 July 2014Section 36 consent granted (Scottish Ministers)
24 September 2015Construction started
15 August 2016Operational

Project details

Technology
wind farm
Capacity
69 MW
Status (REPD)
operational
Record last updated
12 December 2016
Operator or applicant
Scottish Power Renewables
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
23
Address (REPD)
Dersalloch Hill
Council area (by location)
South Ayrshire
Time to decision
469 weeks
REPD reference
4269

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Dersalloch Battery Storage Facilitybattery storage50approved, not built2.1
Enoch Hill 2 Windfarmwind farm10approved, not built3.7
Enoch Hill, Dalmellingtonbattery storage11approved, not built3.7
Wind Farm at Sclenteuch Wind Farmwind farm54approved, not built3.8
Sclenteuch Wind Farmbattery storage45approved, not built3.8
Linfairn Wind Farmwind farm54.4appeal withdrawn4.3
Knockcronal Wind Farmwind farm59.4approved, not built4.9
Knockkippen Wind, Solar & Battery Farmwind farm60approved, not built5.0
Knockkippen Wind, Solar & Battery Farmsolar farm20approved, not built5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3043, -4.4882).