Energy Projects Near You

Knockkippen Wind, Solar & Battery Farm (60 MW)

Knockkippen Wind, Solar & Battery Farm is a 60 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 April 2025, not yet built; the record was last updated on 1 July 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60 MWwind farm
approved, not builtstatus in REPD
1 July 2025record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
24 June 2022Application submitted
30 April 2025Section 36 consent granted (Scottish Ministers)
30 April 2028Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
60 MW
Status (REPD)
approved, not built
Record last updated
1 July 2025
Operator or applicant
Falck Renewables / REG Windpower
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004523
Turbines
12
Turbine height
180 m
Address (REPD)
Knockkippen Moss
Council area (by location)
East Ayrshire
Time to decision
149 weeks
REPD reference
10468

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Knockkippen Wind, Solar & Battery Farmsolar farm20approved, not built<0.1
Burnhead Wind Farmwind farm18.4refused on appeal2.8
Dersalloch Battery Storage Facilitybattery storage50approved, not built3.0
Enoch Hill, Dalmellingtonbattery storage11approved, not built3.0
Enoch Hill 2 Windfarmwind farm10approved, not built3.0
Wind Farm at Sclenteuch Wind Farmwind farm54approved, not built3.2
Sclenteuch Wind Farmbattery storage45approved, not built3.2
Breezy Hill, North Kyle Forest Estatebattery storage40application submitted4.7
Breezy Hill, North Kyle Forest Estatewind farm100application submitted4.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.348, -4.4673).