Dersalloch Battery Storage Facility (50 MW)

Dersalloch Battery Storage Facility is a 50 MW battery storage project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 November 2021, not yet built; the record was last updated on 22 December 2021. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
22 December 2021record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
1 August 2020Application submitted
29 November 2021Section 36 consent granted (Scottish Ministers)
29 November 2026Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
22 December 2021
Operator or applicant
Scottish Power Renewables (UK) Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00002112
Address (REPD)
Wind Farm At Dersalloch B741 Dalmellington Road Straiton, Council Boundary Straiton, Maybole
Council area (by location)
East Ayrshire
Time to decision
69 weeks
REPD reference
8927

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Dersallochwind farm69operational2.1
Enoch Hill, Dalmellingtonbattery storage11approved, not built2.3
Enoch Hill 2 Windfarmwind farm10approved, not built2.3
Wind Farm at Sclenteuch Wind Farmwind farm54approved, not built2.7
Sclenteuch Wind Farmbattery storage45approved, not built2.7
Knockkippen Wind, Solar & Battery Farmsolar farm20approved, not built3.0
Knockkippen Wind, Solar & Battery Farmwind farm60approved, not built3.0
Breezy Hill, North Kyle Forest Estatewind farm100application submitted4.5
Breezy Hill, North Kyle Forest Estatebattery storage40application submitted4.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3217, -4.4776).