Energy Projects Near You

Burnhead Wind Farm (18.4 MW)

Burnhead Wind Farm is an 18.4 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 10 October 2013; the record was last updated on 18 March 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.4 MWwind farm
refused on appealstatus in REPD
18 March 2014record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
1 November 2011Application submitted
18 January 2013Refused by the planning authority
10 October 2013Appeal refused

Project details

Technology
wind farm
Capacity
18.4 MW
Status (REPD)
refused on appeal
Record last updated
18 March 2014
Operator or applicant
Burnhead Wind Farm Ltd
Planning authority
East Ayrshire
Planning application reference
11/0868/PP
Appeal reference
13/0015/REF
Turbines
8
Address (REPD)
Chalmerston, Dalmellington
Council area (by location)
East Ayrshire
Time to decision
63 weeks
REPD reference
3839

Earlier applications for this site

ApplicationMWSubmittedOutcome
Burnhead Wind Farm 09/0180/FL47.530 March 2009withdrawn 19 April 2012

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Knockkippen Wind, Solar & Battery Farmsolar farm20approved, not built2.8
Knockkippen Wind, Solar & Battery Farmwind farm60approved, not built2.8
Enoch Hill 2 Windfarmwind farm10approved, not built2.9
Enoch Hill, Dalmellingtonbattery storage11approved, not built2.9
Breezy Hill, North Kyle Forest Estatewind farm100application submitted3.0
Breezy Hill, North Kyle Forest Estatebattery storage40application submitted3.0
Chalmerstonwind farm50application withdrawn3.3
South Kyle Wind Farm 2wind farm92.4application submitted3.3
North Kyle Energy Projectwind farm206under construction4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3485, -4.4231).