Greenburn Wind Park (10 MW)

Greenburn Wind Park is a 10 MW battery storage project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 April 2023, not yet built; the record was last updated on 13 December 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWbattery storage
approved, not builtstatus in REPD
13 December 2024record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
27 March 2020Application submitted
21 April 2023Section 36 consent granted (Scottish Ministers)
21 April 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (co-located with re)
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
13 December 2024
Operator or applicant
REG Windpower Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00002037
Address (REPD)
Land Adj Former Opencast, Greenburn Wind Park, New Cumnock, Cumnock, Strathclyde
Council area (by location)
East Ayrshire
Time to decision
160 weeks
REPD reference
7159

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Greenburn Wind Parkwind farm67.2approved, not built<0.1
Pencloe Wind Farmwind farm81under construction4.2
High Cumnock Wind Farmwind farm27.2refused on appeal4.7
Glen Water Wind Farmwind farm49.9application submitted5.4
Ashmark Hill Wind Farmwind farm21refused on appeal5.7
Enoch Hillwind farm70operational5.8
Over Hill Wind Farmwind farm36approved, not built5.8
Garleffan Wind Farmwind farm21.6refused on appeal6.7
Ashmark Hill Community Wind Farmwind farm21refused7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4044, -4.269).