Enoch Hill (70 MW wind farm)

Enoch Hill is a 70 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 April 2026; the record was last updated on 4 June 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

70 MWwind farm
operationalstatus in REPD
4 June 2026record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
28 September 2015Application submitted
21 November 2017Appeal lodged
13 September 2019Section 36 consent granted (Scottish Ministers)
13 September 2019Appeal allowed
1 October 2023Construction started
16 April 2026Operational

Project details

Technology
wind farm
Capacity
70 MW
Status (REPD)
operational
Record last updated
4 June 2026
Operator or applicant
E.ON Renewables
Planning authority
Scottish Government (S36)
Planning application reference
EC00005256
Appeal reference
WIN-190-5
Turbines
15
Turbine height
15 m
Address (REPD)
around 14km south west of New Cumnock
Council area (by location)
East Ayrshire
Time to decision
207 weeks
Contracts for Difference
AR5
REPD reference
3502

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Pencloe Wind Farmwind farm81under construction1.6
Ashmark Hill Community Wind Farmwind farm21refused1.7
Ashmark Hill Wind Farmwind farm21refused on appeal2.7
Wind Farm Extensionwind farm22.5application submitted3.5
Glen Water Wind Farmwind farm49.9application submitted5.3
Windy Standard I Repowerwind farm49.6approved, not built5.5
South Kyle Wind Farmwind farm240operational5.6
Greenburn Wind Parkbattery storage10approved, not built5.8
Greenburn Wind Parkwind farm67.2approved, not built5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3558, -4.2351).