Windy Standard I Repower (49.6 MW)

Windy Standard I Repower is a 49.6 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 August 2025, not yet built; the record was last updated on 1 October 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.6 MWwind farm
approved, not builtstatus in REPD
1 October 2025record last updated
Scotlandcouncil area

Planning timeline

DateStage
7 December 2022Application submitted
26 August 2025Section 36 consent granted (Scottish Ministers)

Project details

Technology
wind farm
Capacity
49.6 MW
Status (REPD)
approved, not built
Record last updated
1 October 2025
Operator or applicant
Fred Olsen Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003324
Turbines
8
Turbine height
200 m
Address (REPD)
Carsphairn Forest
Council area (by location)
not known
Time to decision
142 weeks
REPD reference
10539

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Afton Wind Farmwind farm50operational1.7
Brochloch Rig 1 (formerly Windy Standard)wind farm21.6operational1.9
Brochloch Rig (formerly Windy Standard II)wind farm90operational2.1
Windy Rig Wind Farmwind farm43operational4.2
Ashmark Hill Community Wind Farmwind farm21refused4.5
Windy Standard III Wind Farm (Brockloch Rig Phase 2)wind farm87.6under construction4.6
Enoch Hillwind farm70operational5.5
Wind Farm Extensionwind farm22.5application submitted5.6
Euchanhead Wind Farmwind farm126application submitted5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3107, -4.2005).