Brochloch Rig (formerly Windy Standard II) (90 MW)

Brochloch Rig (formerly Windy Standard II) is a 90 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 June 2017; the record was last updated on 27 February 2018. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

90 MWwind farm
operationalstatus in REPD
27 February 2018record last updated
Scotlandcouncil area

Planning timeline

DateStage
14 December 2001Application submitted
13 March 2007Section 36 consent granted (Scottish Ministers)
7 August 2014Construction started
15 June 2017Operational

Project details

Technology
wind farm
Capacity
90 MW
Status (REPD)
operational
Record last updated
27 February 2018
Operator or applicant
Fred Olsen Renewables
Planning authority
Scottish Government (S36)
Planning application reference
02/n/20002
Turbines
30
Turbine height
120 m
Address (REPD)
Near New Cummock
Council area (by location)
not known
Time to decision
274 weeks
REPD reference
4431

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Brochloch Rig 1 (formerly Windy Standard)wind farm21.6operational1.4
Windy Standard I Repowerwind farm49.6approved, not built2.1
Windy Rig Wind Farmwind farm43operational2.5
Afton Wind Farmwind farm50operational2.8
Windy Standard III Wind Farm (Brockloch Rig Phase 2)wind farm87.6under construction3.0
South Kyle Wind Farmwind farm240operational6.3
Euchanhead Wind Farmwind farm126application submitted6.5
Ashmark Hill Community Wind Farmwind farm21refused6.5
Enoch Hillwind farm70operational7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2922, -4.2031).