Afton Wind Farm (50 MW)

Afton Wind Farm is a 50 MW wind farm project in Strathclyde, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2018; the record was last updated on 2 October 2018. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWwind farm
operationalstatus in REPD
2 October 2018record last updated
Scotlandcouncil area

Planning timeline

DateStage
3 November 2004Application submitted
16 October 2014Section 36 consent granted (Scottish Ministers)
16 August 2016Construction started
15 February 2018Operational

Project details

Technology
wind farm
Capacity
50 MW
Status (REPD)
operational
Record last updated
2 October 2018
Operator or applicant
InfraRed Capital Partners/ E.on
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
25
Turbine height
120 m
Address (REPD)
To the south west of New Cumnock adjacent to Afton reservoir
Council area (by location)
not known
Time to decision
519 weeks
REPD reference
4262

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Windy Standard I Repowerwind farm49.6approved, not built1.7
Brochloch Rig 1 (formerly Windy Standard)wind farm21.6operational1.7
Brochloch Rig (formerly Windy Standard II)wind farm90operational2.8
Windy Rig Wind Farmwind farm43operational4.1
Euchanhead Wind Farmwind farm126application submitted4.2
Ashmark Hill Community Wind Farmwind farm21refused4.9
Wind Farm Extensionwind farm22.5application submitted5.4
Windy Standard III Wind Farm (Brockloch Rig Phase 2)wind farm87.6under construction5.8
Enoch Hillwind farm70operational6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3116, -4.1743).