Windy Rig Wind Farm (43 MW)

Windy Rig Wind Farm is a 43 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2021; the record was last updated on 23 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

43 MWwind farm
operationalstatus in REPD
23 September 2020record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
11 June 2019Application submitted
8 November 2019Planning permission granted
1 March 2020Construction started
1 October 2021Operational

Project details

Technology
wind farm
Capacity
43 MW
Status (REPD)
operational
Record last updated
23 September 2020
Operator or applicant
Statkraft UK
Planning authority
Dumfries and Galloway
Planning application reference
19/0938/FUL
Turbines
12
Turbine height
125 m
Address (REPD)
Carsphairn, Castle Douglas,
Council area (by location)
Dumfries and Galloway
Time to decision
21 weeks
REPD reference
7562

Earlier applications for this site

ApplicationMWSubmittedOutcome
Windy Rig Wind Farm 15/P/2/01554320 May 2015replaced by a revised application
Windy Rig Wind Farm 19/0938/FUL4311 June 2019operational since 1 October 2021

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brochloch Rig (formerly Windy Standard II)wind farm90operational2.5
Brochloch Rig 1 (formerly Windy Standard)wind farm21.6operational2.5
Windy Standard III Wind Farm (Brockloch Rig Phase 2)wind farm87.6under construction4.0
Afton Wind Farmwind farm50operational4.1
Windy Standard I Repowerwind farm49.6approved, not built4.2
Lorg Windfarmwind farm64approved, not built5.9
Euchanhead Wind Farmwind farm126application submitted6.2
Shepherd's Rig Wind Farmwind farm81approved, not built6.4
Quantans Hill Wind Farmwind farm57application withdrawn7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2747, -4.1786).