Energy Projects Near You

Windy Standard III Wind Farm (Brockloch Rig Phase 2) (87.6 MW)

Windy Standard III Wind Farm (Brockloch Rig Phase 2) is an 87.6 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 8 April 2025; the record was last updated on 6 May 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

87.6 MWwind farm
under constructionstatus in REPD
6 May 2025record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
9 December 2016Application submitted
2 May 2018Appeal lodged
23 March 2021Section 36 consent granted (Scottish Ministers)
23 March 2021Appeal allowed
8 April 2025Construction started

Project details

Technology
wind farm
Capacity
87.6 MW
Status (REPD)
under construction
Record last updated
6 May 2025
Operator or applicant
Fred Olsen Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00000335
Appeal reference
WIN-170-2003
Turbines
20
Turbine height
180 m
Address (REPD)
Near New Cummock
Council area (by location)
Dumfries and Galloway
Time to decision
224 weeks
Contracts for Difference
AR6
REPD reference
4615

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Brochloch Rig (formerly Windy Standard II)wind farm90operational3.0
Windy Rig Wind Farmwind farm43operational4.0
Brochloch Rig 1 (formerly Windy Standard)wind farm21.6operational4.4
Benbrack Wind Farmwind farm67.1operational4.6
Windy Standard I Repowerwind farm49.6approved, not built4.6
South Kyle Wind Farmwind farm240operational5.6
Afton Wind Farmwind farm50operational5.8
Quantans Hill Wind Farmwind farm57application withdrawn7.0
Quantans Hill Wind Farmwind farm96application submitted7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2764, -4.2417).