Ashmark Hill Community Wind Farm (21 MW)

Ashmark Hill Community Wind Farm is a 21 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 28 September 2018; the record was last updated on 30 November 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWwind farm
refusedstatus in REPD
30 November 2018record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
1 May 2018Application submitted
28 September 2018Refused by the planning authority

Project details

Technology
wind farm
Capacity
21 MW
Status (REPD)
refused
Record last updated
30 November 2018
Operator or applicant
Innogy
Planning authority
East Ayrshire
Planning application reference
18/0354/PP
Turbines
7
Turbine height
135 m
Address (REPD)
Land At Ashmark Hill C90, Afton Road, 5km south of New Cumnock, Mossmark, Strathclyde
Council area (by location)
East Ayrshire
Time to decision
21 weeks
REPD reference
6414

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Enoch Hillwind farm70operational1.7
Wind Farm Extensionwind farm22.5application submitted2.1
Ashmark Hill Wind Farmwind farm21refused on appeal2.2
Pencloe Wind Farmwind farm81under construction3.2
Windy Standard I Repowerwind farm49.6approved, not built4.5
Afton Wind Farmwind farm50operational4.9
Glen Water Wind Farmwind farm49.9application submitted5.1
Hare Hill (East Ayrshire)wind farm13.2operational5.4
Hare Hill Extensionwind farm29.8operational5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3505, -4.2095).