Hare Hill Extension (29.8 MW wind farm)

Hare Hill Extension is a 29.8 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 September 2016; the record was last updated on 2 October 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.8 MWwind farm
operationalstatus in REPD
2 October 2018record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
4 September 2007Application submitted
28 November 2014Planning permission granted
15 October 2015Construction started
15 September 2016Operational

Project details

Technology
wind farm
Capacity
29.8 MW
Status (REPD)
operational
Record last updated
2 October 2018
Operator or applicant
Scottish Power Renewables
Planning authority
East Ayrshire
Planning application reference
07/0809/FL
Turbines
35
Address (REPD)
New Cumnock, East Ayreshire
Council area (by location)
Dumfries and Galloway
Time to decision
377 weeks
REPD reference
4157

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hare Hill (East Ayrshire)wind farm13.2operational<0.1
Wind Farm Extensionwind farm22.5application submitted3.5
Sanquhar 'Six' Community Wind Farmwind farm19.8abandoned4.1
Lethans Wind Farm Extensionwind farm66approved, not built4.3
Ashmark Hill Wind Farmwind farm21refused on appeal4.8
Sandy Knowe Wind Farmwind farm81.6operational4.8
Glen Water Wind Farmwind farm49.9application submitted5.1
Ashmark Hill Community Wind Farmwind farm21refused5.4
Sanquhar Community Windfarmwind farm32.4operational5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3628, -4.1263).