Sanquhar 'Six' Community Wind Farm (19.8 MW)

Sanquhar 'Six' Community Wind Farm is a 19.8 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 21 August 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.8 MWwind farm
abandonedstatus in REPD
21 August 2020record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
27 April 2015Application submitted
15 November 2017Planning permission granted
15 November 2020Permission expired

Project details

Technology
wind farm
Capacity
19.8 MW
Status (REPD)
abandoned
Record last updated
21 August 2020
Operator or applicant
Community Windpower
Planning authority
Dumfries and Galloway
Planning application reference
15/P/3/0166
Turbines
6
Turbine height
130 m
Address (REPD)
Magheughan Rig, Dalmet Hill & , Tynron, Sanquhar, Thornhill, Dumfries & Galloway
Council area (by location)
Dumfries and Galloway
Time to decision
133 weeks
REPD reference
5227

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sanquhar Community Windfarmwind farm32.4operational2.1
Euchanhead Wind Farmwind farm126application submitted3.3
Sanquhar 2 Community Wind Farmwind farm308under construction3.4
Whiteside Hillwind farm25.3operational3.8
Hare Hill Extensionwind farm29.8operational4.1
Hare Hill (East Ayrshire)wind farm13.2operational4.1
Sandy Knowe Wind Farmwind farm81.6operational4.2
Rowancraig North Wind Farmwind farm36application submitted4.9
Ulziesidewind farm40abandoned5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3379, -4.0782).