Hare Hill (East Ayrshire) (13.2 MW wind farm)

Hare Hill (East Ayrshire) is a 13.2 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 November 2000; the record was last updated on 2 October 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.2 MWwind farm
operationalstatus in REPD
2 October 2018record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
10 February 1996Application submitted
12 October 1998Planning permission granted
1 November 2000Operational
24 May 2019Refused by the planning authority

Project details

Technology
wind farm
Capacity
13.2 MW
Status (REPD)
operational
Record last updated
2 October 2018
Operator or applicant
Scottish Power Renewables
Planning authority
East Ayrshire
Planning application reference
not recorded
Turbines
20
Address (REPD)
New Cumnock, East Ayreshire
Council area (by location)
Dumfries and Galloway
Time to decision
139 weeks
REPD reference
2711

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hare Hill Extensionwind farm29.8operational<0.1
Wind Farm Extensionwind farm22.5application submitted3.5
Sanquhar 'Six' Community Wind Farmwind farm19.8abandoned4.1
Lethans Wind Farm Extensionwind farm66approved, not built4.3
Ashmark Hill Wind Farmwind farm21refused on appeal4.8
Sandy Knowe Wind Farmwind farm81.6operational4.8
Glen Water Wind Farmwind farm49.9application submitted5.1
Ashmark Hill Community Wind Farmwind farm21refused5.4
Sanquhar Community Windfarmwind farm32.4operational5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3628, -4.1263).