Glen Water Wind Farm (49.9 MW)

Glen Water Wind Farm is a 49.9 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 16 March 2026, no decision recorded; the record was last updated on 9 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWwind farm
application submittedstatus in REPD
9 April 2026record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
16 March 2026Application submitted

Project details

Technology
wind farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
9 April 2026
Operator or applicant
Glen Water Wind Farm Limited
Planning authority
East Ayrshire
Planning application reference
26/0099/PP
Turbines
6
Turbine height
200 m
Address (REPD)
Glen Water Wind Farm, 2.5km N/O Edge New Cumnock & 3.5km E/O Cumnock, N/O The A76, Cumnock
Council area (by location)
East Ayrshire
Name in REPD
Glen Water - Wind Farm
REPD reference
20651

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ashmark Hill Wind Farmwind farm21refused on appeal2.9
Wind Farm Extensionwind farm22.5application submitted3.8
High Cumnock Wind Farmwind farm27.2refused on appeal4.3
Lethans Wind Farm Extensionwind farm66approved, not built4.3
Garleffan Wind Farmwind farm21.6refused on appeal4.4
Pencloe Wind Farmwind farm81under construction4.9
Ashmark Hill Community Wind Farmwind farm21refused5.1
Hare Hill Extensionwind farm29.8operational5.1
Hare Hill (East Ayrshire)wind farm13.2operational5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3944, -4.1856).