Galawhistle (66 MW wind farm)

Galawhistle is a 66 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2017; the record was last updated on 7 November 2022. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

66 MWwind farm
operationalstatus in REPD
7 November 2022record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
12 March 2010Application submitted
8 August 2012Section 36 consent granted (Scottish Ministers)
18 June 2015Construction started
15 February 2017Operational

Project details

Technology
wind farm
Capacity
66 MW
Status (REPD)
operational
Record last updated
7 November 2022
Operator or applicant
Ventient (formerly Infinis)
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
22
Address (REPD)
7km east of Muirkirk in East Ayrshire and 4km west of Douglas in South Lanarkshire
Council area (by location)
East Ayrshire
Time to decision
126 weeks
REPD reference
4368

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Spireslack Windfarmwind farm59.6application withdrawn1.8
Hare Craig Windfarmwind farm36approved, not built2.3
Cumberhead Wind Farmwind farm48operational3.7
Kennoxhead Wind Farm Extension (Phase 2)wind farm38.4approved, not built3.8
Hagshaw Hill Wind Farmwind farm7.8operational3.9
Hagshaw Hill Wind Farmwind farm7.8operational3.9
Nutberrywind farm60application withdrawn4.5
Hagshaw Hill Wind Farm Extensionwind farm26operational4.6
Kennoxhead Wind Farmwind farm62under construction5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5396, -3.9754).