Energy Projects Near You

Hare Craig Windfarm (36 MW)

Hare Craig Windfarm is a 36 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 July 2022, not yet built; the record was last updated on 19 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36 MWwind farm
approved, not builtstatus in REPD
19 May 2026record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
31 January 2020Application submitted
12 July 2022Planning permission granted
12 July 2027Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
36 MW
Status (REPD)
approved, not built
Record last updated
19 May 2026
Operator or applicant
EnergieKontor UK
Planning authority
East Ayrshire
Planning application reference
20/0001/PP
Turbines
8
Turbine height
230 m
Address (REPD)
Land At Hare Craig, Muirkirk, Cumnock, Strathclyde
Council area (by location)
East Ayrshire
Time to decision
128 weeks
Contracts for Difference
AR5
REPD reference
7261

The scheme also includes 13.9 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Galawhistlewind farm66operational2.3
Spireslack Windfarmwind farm59.6application withdrawn2.5
Nutberrywind farm60application withdrawn2.6
Cumberhead Wind Farmwind farm48operational3.0
Hagshaw Hill Wind Farmwind farm7.8operational4.9
Hagshaw Hill Wind Farmwind farm7.8operational4.9
Hagshaw Hill Wind Farm Extensionwind farm26operational5.0
Kennoxhead Wind Farm Extension (Phase 2)wind farm38.4approved, not built6.0
Nutberry Wind Farmwind farm15operational6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.556, -3.9978).