Energy Projects Near You

Solar, wind and battery projects near Strathaven (ML10)

38 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ML10 (South Lanarkshire): 2 are waiting for a planning decision, 8 approved but not yet running, 13 operational. The largest live scheme is Bankend Rig III Wind Farm (66 MW wind farm, approved on 21 November 2025, not yet built), 8.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

38projects within 10 km
2awaiting a decision
8approved, not running
13operational

Projects within 10 km of ML10

Projects of 1 MW and more (31)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Goodbush Hillwind farmwind farm24application withdrawnupdated Jan 2010Jan 1996—Jan 2010South Lanarkshire0.1
West Dykes Headwind farmwind farm7.6refusedupdated May 2026Jan 2023refused May 2025May 2026South Lanarkshire0.6
Wind turbines at Hawkwood Wind Farm Kype Highway Strathavenwind farmwind farm33application submittedupdated Jan 2025Nov 2024—Jan 2025South Lanarkshire3.5
Dykehead Farm wind turbine 3wind turbinewind turbine2.3application withdrawnupdated Dec 2014Jan 2014—Dec 2014South Lanarkshire5.0
Lochhead Farmwind farmwind farm6operationalupdated Feb 2009Apr 2005granted May 2006Feb 2009South Lanarkshire5.7
Kype Muir Wind Farmwind farmwind farm88.4operationalupdated Oct 2019Aug 2011granted May 2014Oct 2019South Lanarkshire5.7
Kype Muir Wind Farm Extensionwind farmwind farm67.2operationalupdated Nov 2024Oct 2014granted Sep 2016Nov 2024South Lanarkshire5.7
Kittymuir Farmwind farmwind farm1.6permission expiredupdated Sep 2019Aug 2015granted Jun 2016Sep 2019South Lanarkshire6.3
Low Drumclog Farm, Drumclog - 3 Wind Turbineswind farmwind farm20approved, not builtupdated Jun 2026Feb 2022granted Oct 2024Jun 2026South Lanarkshire6.4
Whitelee Wind Farm Battery Storage Extensionbattery storagebattery storage50operationalupdated Feb 2022Jan 2019granted Jun 2019Feb 2022South Lanarkshire6.7
Cornhills Farm, Muttonhole Roadbattery storagebattery storage49.9approved, not builtupdated Mar 2025Mar 2024granted Feb 2025Mar 2025South Lanarkshire6.9
Blantyre Muir Wind Farmwind farmwind farm9operationalupdated Feb 2014Aug 2007granted Nov 2009Feb 2014South Lanarkshire6.9
Blantyre Muir Wind Farm extensionwind farmwind farm7.5operationalupdated Jan 2015Oct 2010granted May 2012Jan 2015South Lanarkshire6.9
High Blackwoodyards Farmwind farmwind farm2refused on appealupdated Oct 2020Nov 2019—Oct 2020South Lanarkshire7.5
Crutherland Farm Wind Turbinewind turbinewind turbine2refusedupdated Dec 2014Apr 2014refused Nov 2014Dec 2014South Lanarkshire7.6
South Priorhill Farmwind turbinewind turbine1.5permission expiredupdated Sep 2020Jun 2015granted Aug 2016Sep 2020South Lanarkshire7.8
Dungavel Hillwind farmwind farm29.9operationalupdated Jan 2016Feb 2006granted Dec 2009Jan 2016South Lanarkshire8.2
Auchrobert Wind Farmwind farmwind farm36operationalupdated Oct 2017Dec 2012granted Apr 2014Oct 2017South Lanarkshire8.2
The Rosti Factorywind turbinewind turbine2.2operationalupdated Apr 2013Apr 2009granted Nov 2010Apr 2013South Lanarkshire8.4
Draffanmarshill Farmwind turbinewind turbine4.2approved, not builtupdated May 2026Sep 2019granted Apr 2025May 2026South Lanarkshire8.5
Marshill Farmwind turbinewind turbine1.5operationalupdated Aug 2016Jul 2012granted Dec 2013Aug 2016South Lanarkshire8.5
Kelvin South Business Park, Hurlawcrook Roadbattery storagebattery storage20application withdrawnupdated Sep 2025Aug 2024—Sep 2025South Lanarkshire8.6
Shaws Farmbattery storagebattery storage5permission expiredupdated Jul 2020Apr 2018—Jul 2020South Lanarkshire8.6
Land associated with Lairfadwind turbinewind turbine1.5application withdrawnupdated May 2016Oct 2014—May 2016South Lanarkshire8.6
Dungavel House, IRC Muirkirk Road Wind Farmwind farmwind farm11.4approved, not builtupdated Oct 2025Aug 2022granted Jan 2025Oct 2025South Lanarkshire8.7
Bankend Rig III Wind Farmwind farmwind farm66approved, not builtupdated Jan 2026Jan 2024granted Nov 2025Jan 2026South Lanarkshire8.8
Stoney Hill Farmwind turbinewind turbine2permission expiredupdated Sep 2020Nov 2015granted Jul 2016Sep 2020South Lanarkshire8.8
Langlands Gate, East Kilbridebattery storagebattery storage30refusedupdated Nov 2025May 2025refused Sep 2025Nov 2025South Lanarkshire8.9
Land associated with Rawhead Farmwind turbinewind turbine1.5application withdrawnupdated May 2016Oct 2014—May 2016South Lanarkshire9.1
West Browncastlewind farmwind farm30operationalupdated Aug 2014Oct 2010granted Jul 2012Aug 2014South Lanarkshire9.1
Ladehead Farmwind farmwind farm2.4operationalupdated May 2018Oct 2012granted Jan 2015May 2018South Lanarkshire9.8
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Strathaven Airfieldrooftop solarrooftop solar—operationalupdated Feb 2021Jan 2021granted Mar 2021Feb 2021South Lanarkshire2.6
East Merkland Farm, Sandfordwind farmwind farm—refusedupdated Jun 2025Feb 2024refused May 2025Jun 2025South Lanarkshire2.7
South Brownhill Farm, High Brownsidewind farmwind farm—refusedupdated Apr 2025Mar 2024refused Feb 2025Apr 2025South Lanarkshire5.4
Logoch Windfarm, East Kilbridewind turbinewind turbine0.5approved, not builtupdated Jul 2024Aug 2023granted Mar 2024Jul 2024South Lanarkshire5.9
Dfds Logistics, Middleton Avenuerooftop solarrooftop solar0.7approved, not built may be out of dateupdated Aug 2023May 2023granted Jul 2023Aug 2023South Lanarkshire8.5
Manson Place, Kelvin Industrial Estaterooftop solarrooftop solar0.2approved, not builtupdated Jul 2023Apr 2023granted Jun 2023Jul 2023South Lanarkshire9.3
Draffanmuir Farmwind turbinewind turbine0.2application submittedupdated May 2026Mar 2026—May 2026South Lanarkshire9.7

Distance from the average position of the ML10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar302100.9
Wind farm191394130
Wind turbine1112214.9
Battery storage5011149.9

MW in pipeline: pending, approved and under-construction capacity.

How South Lanarkshire decides solar, wind and battery applications

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

All projects in South Lanarkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ML10, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.