Dungavel Hill (29.9 MW wind farm)

Dungavel Hill is a 29.9 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 August 2015; the record was last updated on 4 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.9 MWwind farm
operationalstatus in REPD
4 January 2016record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
17 February 2006Application submitted
1 December 2009Planning permission granted
1 May 2014Construction started
28 August 2015Operational

Project details

Technology
wind farm
Capacity
29.9 MW
Status (REPD)
operational
Record last updated
4 January 2016
Operator or applicant
John Laing Environmental Assets Group
Planning authority
South Lanarkshire
Planning application reference
EK/06/0072
Turbines
13
Address (REPD)
Dungavel, Strathaven, Strathclyde
Council area (by location)
South Lanarkshire
Time to decision
198 weeks
REPD reference
4362

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dungavel House, IRC Muirkirk Road Wind Farmwind farm11.4approved, not built2.1
Bankend Rig III Wind Farmwind farm66approved, not built2.1
Bankend Rig II Wind Farmwind farm10.2approved, not built3.3
Bankend Rigwind farm14.3operational4.1
Kype Muir Wind Farmwind farm88.4operational4.7
Kype Muir Wind Farm Extensionwind farm67.2operational4.7
Low Drumclog Farm, Drumclog - 3 Wind Turbineswind farm20approved, not built4.7
Mill Rig Wind Farmwind farm36under construction5.7
Wind turbines at Hawkwood Wind Farm Kype Highway Strathavenwind farm33application submitted6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6086, -4.0977).