Wind turbines at Hawkwood Wind Farm Kype Highway Strathaven (33 MW)
Wind turbines at Hawkwood Wind Farm Kype Highway Strathaven is a 33 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 22 November 2024, no decision recorded; the record was last updated on 10 January 2025.
33 MWwind farm
application submittedstatus in REPD
10 January 2025record last updated
South Lanarkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 22 November 2024 | Application submitted |
Project details
- Technology
- wind farm
- Capacity
- 33 MW
- Status (REPD)
- application submitted
- Record last updated
- 10 January 2025
- Operator or applicant
- Wilson Renewables IV Llp
- Planning authority
- South Lanarkshire
- Planning application reference
- P/24/1420
- Turbines
- 5
- Turbine height
- 200 m
- Address (REPD)
- Hawkwood Wind Farm Kype Highway Strathaven
- Council area (by location)
- South Lanarkshire
- Name in REPD
- Hawkwood Wind Farm, Kype Highway - Wind turbines
- REPD reference
- 11652
Who decides
| Applications | South Lanarkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 89 | 10,236 |
| Refused | 30 (34%) | 19% |
| Solar refused | 2 of 20 | 12% |
| Onshore wind refused | 21 of 56 | 45% |
| Battery storage refused | 7 of 13 | 16% |
| Median time from submission to decision | 47.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Kype Muir Wind Farm Extension | wind farm | 67.2 | operational | 2.2 |
| Kype Muir Wind Farm | wind farm | 88.4 | operational | 2.2 |
| West Dykes Head | wind farm | 7.6 | refused | 3.2 |
| Goodbush Hill | wind farm | 24 | application withdrawn | 3.6 |
| Auchrobert Wind Farm | wind farm | 36 | operational | 4.8 |
| Lochhead Farm | wind farm | 6 | operational | 6.1 |
| Dungavel Hill | wind farm | 29.9 | operational | 6.1 |
| Low Drumclog Farm, Drumclog - 3 Wind Turbines | wind farm | 20 | approved, not built | 6.6 |
| Dungavel House, IRC Muirkirk Road Wind Farm | wind farm | 11.4 | approved, not built | 7.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6527, -4.041).