Energy Projects Near You

Solar, wind and battery projects near Larkhall (ML9)

29 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ML9 (South Lanarkshire): 5 are waiting for a planning decision, 9 approved but not yet running, 8 operational. The largest live scheme is Rogerhill Solar and Battery Energy Storage System (100 MW solar farm, application submitted on 15 January 2025, no decision recorded), 7.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29projects within 10 km
5awaiting a decision
9approved, not running
8operational

Projects within 10 km of ML9

Projects of 1 MW and more (19)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Rosti Factorywind turbinewind turbine2.2operationalupdated Apr 2013Apr 2009granted Nov 2010Apr 2013South Lanarkshire0.4
Shaws Farmbattery storagebattery storage5permission expiredupdated Jul 2020Apr 2018—Jul 2020South Lanarkshire0.9
Kittymuir Farmwind farmwind farm1.6permission expiredupdated Sep 2019Aug 2015granted Jun 2016Sep 2019South Lanarkshire1.8
Lochhead Farmwind farmwind farm6operationalupdated Feb 2009Apr 2005granted May 2006Feb 2009South Lanarkshire3.3
Draffanmarshill Farmwind turbinewind turbine4.2approved, not builtupdated May 2026Sep 2019granted Apr 2025May 2026South Lanarkshire4.7
Marshill Farmwind turbinewind turbine1.5operationalupdated Aug 2016Jul 2012granted Dec 2013Aug 2016South Lanarkshire4.7
Wishaw Battery Storage Facilitybattery storagebattery storage50operationalupdated May 2022Sep 2020granted Nov 2020May 2022North Lanarkshire5.3
Cornhills Farm, Muttonhole Roadbattery storagebattery storage49.9approved, not builtupdated Mar 2025Mar 2024granted Feb 2025Mar 2025South Lanarkshire7.0
West Dykes Headwind farmwind farm7.6refusedupdated May 2026Jan 2023refused May 2025May 2026South Lanarkshire7.6
Rogerhill Solar and Battery Energy Storage Systemsolar farmsolar farm100application submittedupdated Jan 2025Jan 2025—Jan 2025South Lanarkshire7.6
Rogerhill Solar and Battery Energy Storage Systembattery storagebattery storage100application submittedupdated Jan 2025Jan 2025—Jan 2025South Lanarkshire7.6
High Blackwoodyards Farmwind farmwind farm2refused on appealupdated Oct 2020Nov 2019—Oct 2020South Lanarkshire7.7
Blantyre Muir Wind Farmwind farmwind farm9operationalupdated Feb 2014Aug 2007granted Nov 2009Feb 2014South Lanarkshire7.9
Blantyre Muir Wind Farm extensionwind farmwind farm7.5operationalupdated Jan 2015Oct 2010granted May 2012Jan 2015South Lanarkshire7.9
Goodbush Hillwind farmwind farm24application withdrawnupdated Jan 2010Jan 1996—Jan 2010South Lanarkshire8.0
Ladehead Farmwind farmwind farm2.4operationalupdated May 2018Oct 2012granted Jan 2015May 2018South Lanarkshire8.8
Wind turbines at Hawkwood Wind Farm Kype Highway Strathavenwind farmwind farm33application submittedupdated Jan 2025Nov 2024—Jan 2025South Lanarkshire9.2
Watsonhead Wind Farmwind farmwind farm8.4operationalupdated Oct 2025Feb 2018granted Feb 2020Oct 2025North Lanarkshire9.5
Bogsidewind farmwind farm2.3refusedupdated Apr 2009Jul 2005refused Jun 2008Apr 2009South Lanarkshire9.7
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dfds Logistics, Middleton Avenuerooftop solarrooftop solar0.7approved, not built may be out of dateupdated Aug 2023May 2023granted Jul 2023Aug 2023South Lanarkshire0.5
Skellyton Wastewater Treatment Workssolar farmsolar farm0.2approved, not built may be out of dateupdated Mar 2022Feb 2022granted Jul 2022Mar 2022South Lanarkshire2.5
Draffanmuir Farmwind turbinewind turbine0.2application submittedupdated May 2026Mar 2026—May 2026South Lanarkshire4.6
Scotland Laundry, Canyon Roadrooftop solarrooftop solar0.2application submitted may be out of dateupdated Aug 2024Jul 2024—Aug 2024North Lanarkshire5.3
East Merkland Farm, Sandfordwind farmwind farm—refusedupdated Jun 2025Feb 2024refused May 2025Jun 2025South Lanarkshire8.0
David Lloyd, Mote Hillrooftop solarrooftop solar0.7approved, not builtupdated Oct 2023Sep 2023granted Oct 2023Oct 2023South Lanarkshire8.4
Auchtygemmel Farm, Muirhouse Roadwind farmwind farm—approved, not builtupdated May 2025Dec 2024granted Apr 2025May 2025South Lanarkshire9.1
Glasgow Road, Blantyrerooftop solarrooftop solar0.4approved, not built may be out of dateupdated Feb 2023Nov 2022granted Feb 2023Feb 2023South Lanarkshire9.8
Stanley Boulevard, Hamilton Tech Park - Roof Mounted Photovoltaic Panelsrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024South Lanarkshire9.9
International House, Stanley Boulevardrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2023Jun 2023granted Jun 2023Jul 2023South Lanarkshire9.9

Distance from the average position of the ML9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm21100100
Rooftop solar615002.4
Wind farm13115433
Wind turbine411204.4
Battery storage41110150

MW in pipeline: pending, approved and under-construction capacity.

How South Lanarkshire decides solar, wind and battery applications

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

All projects in South Lanarkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ML9, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.