Solar, wind and battery projects near Hamilton (ML3)
47 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ML3 (South Lanarkshire): 5 are waiting for a planning decision, 23 approved but not yet running, 7 operational. The largest live scheme is Newarthill Energy Park (300 MW battery storage, approved on 4 February 2025, not yet built), 9.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ML3
Projects of 1 MW and more (24)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Cornhills Farm, Muttonhole Roadbattery storage | battery storage | 49.9 | approved, not builtupdated Mar 2025 | Mar 2024 | granted Feb 2025 | Mar 2025 | South Lanarkshire | 3.3 |
| Blantyre Muir Wind Farmwind farm | wind farm | 9 | operationalupdated Feb 2014 | Aug 2007 | granted Nov 2009 | Feb 2014 | South Lanarkshire | 3.8 |
| Blantyre Muir Wind Farm extensionwind farm | wind farm | 7.5 | operationalupdated Jan 2015 | Oct 2010 | granted May 2012 | Jan 2015 | South Lanarkshire | 3.8 |
| Malcolmwood Farm, Loanend Roadbattery storage | battery storage | 49.5 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | South Lanarkshire | 4.5 |
| Crutherland Farm Wind Turbinewind turbine | wind turbine | 2 | refusedupdated Dec 2014 | Apr 2014 | refused Nov 2014 | Dec 2014 | South Lanarkshire | 5.8 |
| Newton Farm, Westburn Roadbattery storage | battery storage | 40 | refusedupdated Apr 2026 | Jul 2025 | refused Feb 2026 | Apr 2026 | South Lanarkshire | 6.9 |
| East Rogerton Cottage, Markethill Roadbattery storage | battery storage | 55 | approved, not builtupdated Jun 2026 | Sep 2025 | granted Feb 2026 | Jun 2026 | South Lanarkshire | 7.3 |
| Gilbertfield Farm, Gilbertfield Roadbattery storage | battery storage | 40 | refusedupdated Dec 2025 | Apr 2025 | refused Oct 2025 | Dec 2025 | South Lanarkshire | 7.3 |
| Wishaw Battery Storage Facilitybattery storage | battery storage | 50 | operationalupdated May 2022 | Sep 2020 | granted Nov 2020 | May 2022 | North Lanarkshire | 7.3 |
| Brew Dog Brewery, Condor Glenrooftop solar | rooftop solar | 1.3 | approved, not built may be out of dateupdated May 2023 | Apr 2023 | granted May 2023 | May 2023 | North Lanarkshire | 7.3 |
| Kittymuir Farmwind farm | wind farm | 1.6 | permission expiredupdated Sep 2019 | Aug 2015 | granted Jun 2016 | Sep 2019 | South Lanarkshire | 7.7 |
| The Rosti Factorywind turbine | wind turbine | 2.2 | operationalupdated Apr 2013 | Apr 2009 | granted Nov 2010 | Apr 2013 | South Lanarkshire | 7.7 |
| Kelvin South Business Park, Hurlawcrook Roadbattery storage | battery storage | 20 | application withdrawnupdated Sep 2025 | Aug 2024 | — | Sep 2025 | South Lanarkshire | 8.0 |
| Langlands Gate, East Kilbridebattery storage | battery storage | 30 | refusedupdated Nov 2025 | May 2025 | refused Sep 2025 | Nov 2025 | South Lanarkshire | 8.1 |
| Shaws Farmbattery storage | battery storage | 5 | permission expiredupdated Jul 2020 | Apr 2018 | — | Jul 2020 | South Lanarkshire | 8.2 |
| Dykehead Farm wind turbine 3wind turbine | wind turbine | 2.3 | application withdrawnupdated Dec 2014 | Jan 2014 | — | Dec 2014 | South Lanarkshire | 8.5 |
| Highflat Battery Energy Storagebattery storage | battery storage | 19.9 | application withdrawnupdated Nov 2018 | Apr 2018 | — | Nov 2018 | South Lanarkshire | 9.1 |
| Lochhead Farmwind farm | wind farm | 6 | operationalupdated Feb 2009 | Apr 2005 | granted May 2006 | Feb 2009 | South Lanarkshire | 9.4 |
| Newarthill Energy Parkbattery storage | battery storage | 300 | approved, not builtupdated Aug 2025 | Nov 2023 | granted Feb 2025 | Aug 2025 | North Lanarkshire | 9.4 |
| Castlemilk and Carmunnock Community Windpark Trustwind turbine | wind turbine | 2.5 | refusedupdated Mar 2015 | Aug 2013 | refused Nov 2013 | Mar 2015 | South Lanarkshire | 9.7 |
| Newhouse, Biggar Road -Solar Arraysolar farm | solar farm | 3.5 | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | North Lanarkshire | 9.8 |
| Goodbush Hillwind farm | wind farm | 24 | application withdrawnupdated Jan 2010 | Jan 1996 | — | Jan 2010 | South Lanarkshire | 9.9 |
| West Dykes Headwind farm | wind farm | 7.6 | refusedupdated May 2026 | Jan 2023 | refused May 2025 | May 2026 | South Lanarkshire | 9.9 |
| Biggar Road, Clelandbattery storage | battery storage | 30 | approved, not builtupdated Mar 2025 | Aug 2024 | granted Mar 2025 | Mar 2025 | North Lanarkshire | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| David Lloyd, Mote Hillrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Oct 2023 | Sep 2023 | granted Oct 2023 | Oct 2023 | South Lanarkshire | 2.0 |
| Glasgow Road, Blantyrerooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Feb 2023 | Nov 2022 | granted Feb 2023 | Feb 2023 | South Lanarkshire | 2.4 |
| Stanley Boulevard, Hamilton Tech Park - Roof Mounted Photovoltaic Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Mar 2024 | Apr 2024 | South Lanarkshire | 2.6 |
| International House, Stanley Boulevardrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jul 2023 | Jun 2023 | granted Jun 2023 | Jul 2023 | South Lanarkshire | 2.6 |
| Clyde Avenue, Bothwellsolar farm | solar farm | 0.7 | approved, not built may be out of dateupdated Apr 2023 | Oct 2022 | granted Mar 2023 | Apr 2023 | South Lanarkshire | 3.6 |
| Allers Wastewater Treatment Works, Barrie Roadsolar farm | solar farm | 0.2 | operationalupdated Feb 2025 | Feb 2024 | granted Apr 2024 | Feb 2025 | South Lanarkshire | 5.1 |
| Skellyton Wastewater Treatment Workssolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Mar 2022 | Feb 2022 | granted Jul 2022 | Mar 2022 | South Lanarkshire | 6.5 |
| Scotland Laundry, Canyon Roadrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Aug 2024 | Jul 2024 | — | Aug 2024 | North Lanarkshire | 6.7 |
| Reynolds Building, Scottish Enterprise Technology Park- Solar Panlesrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | South Lanarkshire | 6.9 |
| Avondale House, Phoenix Crescentrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | North Lanarkshire | 7.0 |
| Manson Place, Kelvin Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2023 | Apr 2023 | granted Jun 2023 | Jul 2023 | South Lanarkshire | 7.0 |
| Duart House, Finch Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | North Lanarkshire | 7.1 |
| Sainsburys, Kingsgate Retail Parkrooftop solar | rooftop solar | — | application submitted may be out of dateupdated Sep 2023 | Aug 2023 | — | Sep 2023 | South Lanarkshire | 7.2 |
| Tannochside Drive, Tannochside Parkrooftop solar | rooftop solar | — | approved, not builtupdated Nov 2022 | Oct 2022 | granted Nov 2022 | Nov 2022 | North Lanarkshire | 7.4 |
| Stroud Road East, Kilbriderooftop solar | rooftop solar | — | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | South Lanarkshire | 7.6 |
| Dfds Logistics, Middleton Avenuerooftop solar | rooftop solar | 0.7 | approved, not built may be out of dateupdated Aug 2023 | May 2023 | granted Jul 2023 | Aug 2023 | South Lanarkshire | 7.6 |
| Hollywood Bowl Showcase Leisure Park, Barrbridge Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Aug 2022 | granted Aug 2022 | Nov 2022 | North Lanarkshire | 8.7 |
| Scottish Fire & Rescue Service, Westburn Drive Solar Array & BESSsolar farm | solar farm | 0.6 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | South Lanarkshire | 8.9 |
| Westburn Drive, Cambuslangrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | South Lanarkshire | 8.9 |
| Scottish Fire & Rescue Service, Westburn Drive Solar Array & BESSbattery storage | battery storage | — | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Glasgow City | 9.1 |
| Henry Colbeck Officerooftop solar | rooftop solar | 0.2 | operationalupdated Oct 2019 | Apr 2019 | granted May 2019 | Oct 2019 | North Lanarkshire | 9.7 |
| Newhouse, Biggar Roadbattery storage | battery storage | — | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | North Lanarkshire | 9.9 |
| Cambuslang Investment Park, Clydesmill Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Glasgow City | 10.0 |
Distance from the average position of the ML3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 5 | 1 | 3 | 1 | 0 | 4.9 |
| Rooftop solar | 18 | 2 | 15 | 1 | 0 | 5.4 |
| Wind farm | 6 | 0 | 0 | 3 | 1 | 0 |
| Wind turbine | 4 | 0 | 0 | 1 | 2 | 0 |
| Battery storage | 14 | 2 | 5 | 1 | 3 | 484 |
MW in pipeline: pending, approved and under-construction capacity.
How South Lanarkshire decides solar, wind and battery applications
| Applications | South Lanarkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 89 | 10,236 |
| Refused | 30 (34%) | 19% |
| Solar refused | 2 of 20 | 12% |
| Onshore wind refused | 21 of 56 | 45% |
| Battery storage refused | 7 of 13 | 16% |
| Median time from submission to decision | 47.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 5 | — |
All projects in South Lanarkshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ML3, 9 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.