Energy Projects Near You

Cornhills Farm, Muttonhole Road (49.9 MW battery storage)

Cornhills Farm, Muttonhole Road is a 49.9 MW battery storage project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 February 2025, not yet built; the record was last updated on 24 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
24 March 2025record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
12 March 2024Application submitted
7 February 2025Planning permission granted
7 February 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
24 March 2025
Operator or applicant
Big Battery (Sheriff Faulds Farm 1) Limited
Planning authority
South Lanarkshire
Planning application reference
P/23/1613
Address (REPD)
Cornhills Farm Muttonhole Road Hamilton
Council area (by location)
South Lanarkshire
Time to decision
47 weeks
Name in REPD
Cornhills Farm, Muttonhole Road - Battery Storage
REPD reference
11647

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blantyre Muir Wind Farm extensionwind farm7.5operational0.9
Blantyre Muir Wind Farmwind farm9operational0.9
Kelvin South Business Park, Hurlawcrook Roadbattery storage20application withdrawn5.8
Langlands Gate, East Kilbridebattery storage30refused5.9
Malcolmwood Farm, Loanend Roadbattery storage49.5application submitted6.1
Goodbush Hillwind farm24application withdrawn6.8
West Dykes Headwind farm7.6refused7.0
East Rogerton Cottage, Markethill Roadbattery storage55approved, not built7.5
Lochhead Farmwind farm6operational7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7423, -4.0756).