Solar, wind and battery projects near East Kilbride (G74)
51 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of G74 (South Lanarkshire): 5 are waiting for a planning decision, 25 approved but not yet running, 7 operational. The largest live scheme is Downiebrae Road, Rutherglen (150 MW battery storage, approved on 3 September 2025, not yet built), 7.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of G74
Projects of 1 MW and more (28)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| East Rogerton Cottage, Markethill Roadbattery storage | battery storage | 55 | approved, not builtupdated Jun 2026 | Sep 2025 | granted Feb 2026 | Jun 2026 | South Lanarkshire | 1.9 |
| Highflat Battery Energy Storagebattery storage | battery storage | 19.9 | application withdrawnupdated Nov 2018 | Apr 2018 | — | Nov 2018 | South Lanarkshire | 2.8 |
| Castlemilk and Carmunnock Community Windpark Trustwind turbine | wind turbine | 2.5 | refusedupdated Mar 2015 | Aug 2013 | refused Nov 2013 | Mar 2015 | South Lanarkshire | 3.1 |
| Langlands Gate, East Kilbridebattery storage | battery storage | 30 | refusedupdated Nov 2025 | May 2025 | refused Sep 2025 | Nov 2025 | South Lanarkshire | 3.6 |
| Kelvin South Business Park, Hurlawcrook Roadbattery storage | battery storage | 20 | application withdrawnupdated Sep 2025 | Aug 2024 | — | Sep 2025 | South Lanarkshire | 3.9 |
| Cathkin Braes Wind Farm (Castlemilk)wind turbine | wind turbine | 3 | operationalupdated Sep 2013 | Sep 2012 | granted Jan 2013 | Sep 2013 | South Lanarkshire | 4.0 |
| Gilbertfield Farm, Gilbertfield Roadbattery storage | battery storage | 40 | refusedupdated Dec 2025 | Apr 2025 | refused Oct 2025 | Dec 2025 | South Lanarkshire | 4.0 |
| Crutherland Farm Wind Turbinewind turbine | wind turbine | 2 | refusedupdated Dec 2014 | Apr 2014 | refused Nov 2014 | Dec 2014 | South Lanarkshire | 4.4 |
| Malcolmwood Farm, Loanend Roadbattery storage | battery storage | 49.5 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | South Lanarkshire | 4.7 |
| Blantyre Muir Wind Farmwind farm | wind farm | 9 | operationalupdated Feb 2014 | Aug 2007 | granted Nov 2009 | Feb 2014 | South Lanarkshire | 6.2 |
| Blantyre Muir Wind Farm extensionwind farm | wind farm | 7.5 | operationalupdated Jan 2015 | Oct 2010 | granted May 2012 | Jan 2015 | South Lanarkshire | 6.2 |
| Newton Farm, Westburn Roadbattery storage | battery storage | 40 | refusedupdated Apr 2026 | Jul 2025 | refused Feb 2026 | Apr 2026 | South Lanarkshire | 6.7 |
| Glasgow Road, Eagleshambattery storage | battery storage | 40 | approved, not builtupdated May 2025 | Jan 2025 | granted Apr 2025 | May 2025 | East Renfrewshire | 6.8 |
| Dunwan Dam, Eaglesham Wind Farmwind farm | wind farm | 30 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | East Renfrewshire | 6.9 |
| Cornhills Farm, Muttonhole Roadbattery storage | battery storage | 49.9 | approved, not builtupdated Mar 2025 | Mar 2024 | granted Feb 2025 | Mar 2025 | South Lanarkshire | 6.9 |
| Land associated with Rawhead Farmwind turbine | wind turbine | 1.5 | application withdrawnupdated May 2016 | Oct 2014 | — | May 2016 | South Lanarkshire | 7.2 |
| Land associated with Lairfadwind turbine | wind turbine | 1.5 | application withdrawnupdated May 2016 | Oct 2014 | — | May 2016 | South Lanarkshire | 7.2 |
| Over Enoch Farmwind farm | wind farm | 6.5 | abandonedupdated Dec 2012 | May 2003 | granted Sep 2004 | Dec 2012 | East Renfrewshire | 7.3 |
| Ardoch and Over Enoch Wind Farm (Ardoch)wind farm | wind farm | 7.2 | operationalupdated Oct 2016 | May 2012 | granted Jul 2012 | Oct 2016 | East Renfrewshire | 7.3 |
| Dykehead Farm wind turbine 3wind turbine | wind turbine | 2.3 | application withdrawnupdated Dec 2014 | Jan 2014 | — | Dec 2014 | South Lanarkshire | 7.4 |
| Ardoch Farm (East Renfrewshire)wind farm | wind farm | 3.9 | abandonedupdated Dec 2011 | Jan 2003 | granted Sep 2004 | Dec 2011 | East Renfrewshire | 7.5 |
| Seath Road, Rutherglenbattery storage | battery storage | 50 | refusedupdated Apr 2024 | Sep 2023 | refused Mar 2024 | Apr 2024 | South Lanarkshire | 7.7 |
| Dalmarnock Roadbattery storage | battery storage | 40 | approved, not built may be out of dateupdated Mar 2021 | Sep 2021 | granted Feb 2022 | Mar 2021 | South Lanarkshire | 7.8 |
| Downiebrae Road, Rutherglenbattery storage | battery storage | 150 | approved, not builtupdated Oct 2025 | Jan 2025 | granted Sep 2025 | Oct 2025 | Glasgow City | 7.8 |
| Ardoch and Over Enoch Wind Farm (Over Enoch)wind farm | wind farm | 4.3 | operationalupdated Oct 2016 | Sep 2011 | granted Apr 2012 | Oct 2016 | East Renfrewshire | 8.1 |
| Whitelee Wind Farm Battery Storage Extensionbattery storage | battery storage | 50 | operationalupdated Feb 2022 | Jan 2019 | granted Jun 2019 | Feb 2022 | South Lanarkshire | 8.2 |
| Bonnyton, Kirkton Moor Roadsolar farm | solar farm | 28 | approved, not builtupdated Apr 2026 | Jul 2025 | granted Feb 2026 | Apr 2026 | East Renfrewshire | 9.0 |
| Moorhouse (Eaglesham)wind farm | wind farm | 47.5 | refused on appealupdated Jan 2013 | Apr 2010 | refused Apr 2012 | Jan 2013 | East Renfrewshire | 9.4 |
Smaller schemes under 1 MW, mostly rooftop solar (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Sainsburys, Kingsgate Retail Parkrooftop solar | rooftop solar | — | application submitted may be out of dateupdated Sep 2023 | Aug 2023 | — | Sep 2023 | South Lanarkshire | 1.6 |
| Reynolds Building, Scottish Enterprise Technology Park- Solar Panlesrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | South Lanarkshire | 1.7 |
| Stroud Road East, Kilbriderooftop solar | rooftop solar | — | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | South Lanarkshire | 2.2 |
| Tennant Avenue College, East Kilbriderooftop solar | rooftop solar | 0.9 | under constructionupdated Dec 2022 | Sep 2022 | granted May 2023 | Dec 2022 | South Lanarkshire | 2.5 |
| Manson Place, Kelvin Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2023 | Apr 2023 | granted Jun 2023 | Jul 2023 | South Lanarkshire | 2.7 |
| Allers Wastewater Treatment Works, Barrie Roadsolar farm | solar farm | 0.2 | operationalupdated Feb 2025 | Feb 2024 | granted Apr 2024 | Feb 2025 | South Lanarkshire | 2.9 |
| Police Training And Recruitment Centre, Eaglesham Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2023 | Feb 2023 | granted Mar 2023 | Mar 2023 | South Lanarkshire | 4.2 |
| Stanley Boulevard, Hamilton Tech Park - Roof Mounted Photovoltaic Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Mar 2024 | Apr 2024 | South Lanarkshire | 5.2 |
| International House, Stanley Boulevardrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jul 2023 | Jun 2023 | granted Jun 2023 | Jul 2023 | South Lanarkshire | 5.2 |
| Scottish Fire & Rescue Service, Westburn Drive Solar Array & BESSsolar farm | solar farm | 0.6 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | South Lanarkshire | 6.1 |
| Westburn Drive, Cambuslangrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | South Lanarkshire | 6.2 |
| Scottish Fire & Rescue Service, Westburn Drive Solar Array & BESSbattery storage | battery storage | — | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Glasgow City | 6.5 |
| Glasgow Road, Blantyrerooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Feb 2023 | Nov 2022 | granted Feb 2023 | Feb 2023 | South Lanarkshire | 6.6 |
| Linn Products, Glasgow Roadsolar farm | solar farm | 0.5 | approved, not builtupdated Mar 2025 | Feb 2025 | granted Mar 2025 | Mar 2025 | East Renfrewshire | 6.8 |
| Cunninghame Road, Farm Castle Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Sep 2022 | Aug 2022 | granted Sep 2022 | Sep 2022 | South Lanarkshire | 7.1 |
| Clyde Avenue, Bothwellsolar farm | solar farm | 0.7 | approved, not built may be out of dateupdated Apr 2023 | Oct 2022 | granted Mar 2023 | Apr 2023 | South Lanarkshire | 7.1 |
| Cambuslang Investment Park, Clydesmill Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Glasgow City | 7.2 |
| Clyde Gateway Trade Park, Dalmarnock Roadbattery storage | battery storage | — | application submitted | May 2026 | — | — | South Lanarkshire | 7.6 |
| Clyde Gateway Developments Limited - D2 Grids Demonstrator Projectsolar farm | solar farm | — | application submitted may be out of dateupdated Feb 2022 | Dec 2022 | — | Feb 2022 | South Lanarkshire | 7.9 |
| Dalmarnock Wastewater Treatment Worksrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated May 2021 | Apr 2021 | granted Jun 2021 | May 2021 | Glasgow City | 8.1 |
| David Lloyd, Mote Hillrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Oct 2023 | Sep 2023 | granted Oct 2023 | Oct 2023 | South Lanarkshire | 8.4 |
| Logoch Windfarm, East Kilbridewind turbine | wind turbine | 0.5 | approved, not builtupdated Jul 2024 | Aug 2023 | granted Mar 2024 | Jul 2024 | South Lanarkshire | 9.2 |
| David Lloyd Leisure Health Club, Stewarton Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2024 | Oct 2023 | granted Dec 2023 | Jan 2024 | East Renfrewshire | 9.8 |
Distance from the average position of the G74 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 6 | 1 | 4 | 1 | 0 | 29.7 |
| Rooftop solar | 15 | 1 | 14 | 0 | 0 | 4.6 |
| Wind farm | 8 | 1 | 0 | 4 | 1 | 30 |
| Wind turbine | 7 | 0 | 1 | 1 | 2 | 0.5 |
| Battery storage | 15 | 2 | 6 | 1 | 4 | 384 |
MW in pipeline: pending, approved and under-construction capacity.
How South Lanarkshire decides solar, wind and battery applications
| Applications | South Lanarkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 89 | 10,236 |
| Refused | 30 (34%) | 19% |
| Solar refused | 2 of 20 | 12% |
| Onshore wind refused | 21 of 56 | 45% |
| Battery storage refused | 7 of 13 | 16% |
| Median time from submission to decision | 47.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 5 | — |
All projects in South Lanarkshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near G74, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.