Whitelee Wind Farm Battery Storage Extension (50 MW)

Whitelee Wind Farm Battery Storage Extension is a 50 MW battery storage project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2021; the record was last updated on 21 February 2022. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
operationalstatus in REPD
21 February 2022record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
30 January 2019Application submitted
10 June 2019Section 36 consent granted (Scottish Ministers)
1 October 2020Construction started
1 October 2021Operational

Project details

Technology
battery storage (co-located with re)
Capacity
50 MW
Status (REPD)
operational
Record last updated
21 February 2022
Operator or applicant
Scottish Power Renewables (formerly Arcus Consultancy Services)
Planning authority
Scottish Government (S36)
Planning application reference
ECU00000729
Address (REPD)
Eaglesham Moor, Whitelee Forest, Fenwick Moor, East Kilbride, South of Glasgow
Council area (by location)
South Lanarkshire
Time to decision
19 weeks
REPD reference
7174

Recorded together with Whitelee (322 MW wind farm, operational).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Kelvin South Business Park, Hurlawcrook Roadbattery storage20application withdrawn4.3
Langlands Gate, East Kilbridebattery storage30refused4.5
West Browncastlewind farm30operational4.7
Ardoch and Over Enoch Wind Farm (Ardoch)wind farm7.2operational5.8
Low Drumclog Farm, Drumclog - 3 Wind Turbineswind farm20approved, not built6.2
Over Enoch Farmwind farm6.5abandoned6.3
Goodbush Hillwind farm24application withdrawn6.6
Calder Water Community Wind Farmwind farm28operational6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6955, -4.1714).