Langlands Gate, East Kilbride (30 MW battery storage)

Langlands Gate, East Kilbride is a 30 MW battery storage project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 9 September 2025; the record was last updated on 7 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
refusedstatus in REPD
7 November 2025record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
20 May 2025Application submitted
9 September 2025Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
refused
Record last updated
7 November 2025
Operator or applicant
Advanced Grid Solutions Limited
Planning authority
South Lanarkshire
Planning application reference
P/25/0555
Address (REPD)
Langlands Gate, East Kilbride, Glasgow
Council area (by location)
South Lanarkshire
Time to decision
16 weeks
Name in REPD
Langlands Gate, East Kilbride - Battery Energy Storage
REPD reference
19806

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kelvin South Business Park, Hurlawcrook Roadbattery storage20application withdrawn0.3
Whitelee Wind Farm Battery Storage Extensionbattery storage50operational4.5
Blantyre Muir Wind Farm extensionwind farm7.5operational5.0
Blantyre Muir Wind Farmwind farm9operational5.0
East Rogerton Cottage, Markethill Roadbattery storage55approved, not built5.5
Ardoch and Over Enoch Wind Farm (Ardoch)wind farm7.2operational5.6
Over Enoch Farmwind farm6.5abandoned5.8
Cornhills Farm, Muttonhole Roadbattery storage49.9approved, not built5.9
Highflat Battery Energy Storagebattery storage19.9application withdrawn6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7363, -4.1697).