Energy Projects Near You

Solar, wind and battery projects near East Kilbride (G75)

61 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of G75 (South Lanarkshire): 5 are waiting for a planning decision, 26 approved but not yet running, 13 operational. The largest live scheme is Downiebrae Road, Rutherglen (150 MW battery storage, approved on 3 September 2025, not yet built), 9.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

61projects within 10 km
5awaiting a decision
26approved, not running
13operational

Projects within 10 km of G75

Projects of 1 MW and more (38)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Langlands Gate, East Kilbridebattery storagebattery storage30refusedupdated Nov 2025May 2025refused Sep 2025Nov 2025South Lanarkshire2.5
Kelvin South Business Park, Hurlawcrook Roadbattery storagebattery storage20application withdrawnupdated Sep 2025Aug 2024—Sep 2025South Lanarkshire2.8
East Rogerton Cottage, Markethill Roadbattery storagebattery storage55approved, not builtupdated Jun 2026Sep 2025granted Feb 2026Jun 2026South Lanarkshire4.4
Crutherland Farm Wind Turbinewind turbinewind turbine2refusedupdated Dec 2014Apr 2014refused Nov 2014Dec 2014South Lanarkshire4.6
Castlemilk and Carmunnock Community Windpark Trustwind turbinewind turbine2.5refusedupdated Mar 2015Aug 2013refused Nov 2013Mar 2015South Lanarkshire4.6
Highflat Battery Energy Storagebattery storagebattery storage19.9application withdrawnupdated Nov 2018Apr 2018—Nov 2018South Lanarkshire4.6
Dunwan Dam, Eaglesham Wind Farmwind farmwind farm30application submittedupdated Sep 2025Aug 2025—Sep 2025East Renfrewshire4.7
Over Enoch Farmwind farmwind farm6.5abandonedupdated Dec 2012May 2003granted Sep 2004Dec 2012East Renfrewshire4.7
Ardoch and Over Enoch Wind Farm (Ardoch)wind farmwind farm7.2operationalupdated Oct 2016May 2012granted Jul 2012Oct 2016East Renfrewshire4.7
Land associated with Rawhead Farmwind turbinewind turbine1.5application withdrawnupdated May 2016Oct 2014—May 2016South Lanarkshire4.9
Ardoch Farm (East Renfrewshire)wind farmwind farm3.9abandonedupdated Dec 2011Jan 2003granted Sep 2004Dec 2011East Renfrewshire4.9
Glasgow Road, Eagleshambattery storagebattery storage40approved, not builtupdated May 2025Jan 2025granted Apr 2025May 2025East Renfrewshire4.9
Land associated with Lairfadwind turbinewind turbine1.5application withdrawnupdated May 2016Oct 2014—May 2016South Lanarkshire5.0
Cathkin Braes Wind Farm (Castlemilk)wind turbinewind turbine3operationalupdated Sep 2013Sep 2012granted Jan 2013Sep 2013South Lanarkshire5.3
Ardoch and Over Enoch Wind Farm (Over Enoch)wind farmwind farm4.3operationalupdated Oct 2016Sep 2011granted Apr 2012Oct 2016East Renfrewshire5.5
Whitelee Wind Farm Battery Storage Extensionbattery storagebattery storage50operationalupdated Feb 2022Jan 2019granted Jun 2019Feb 2022South Lanarkshire6.4
Dykehead Farm wind turbine 3wind turbinewind turbine2.3application withdrawnupdated Dec 2014Jan 2014—Dec 2014South Lanarkshire6.4
Gilbertfield Farm, Gilbertfield Roadbattery storagebattery storage40refusedupdated Dec 2025Apr 2025refused Oct 2025Dec 2025South Lanarkshire6.5
Blantyre Muir Wind Farmwind farmwind farm9operationalupdated Feb 2014Aug 2007granted Nov 2009Feb 2014South Lanarkshire7.0
Blantyre Muir Wind Farm extensionwind farmwind farm7.5operationalupdated Jan 2015Oct 2010granted May 2012Jan 2015South Lanarkshire7.0
Bonnyton, Kirkton Moor Roadsolar farmsolar farm28approved, not builtupdated Apr 2026Jul 2025granted Feb 2026Apr 2026East Renfrewshire7.1
Malcolmwood Farm, Loanend Roadbattery storagebattery storage49.5application submittedupdated Sep 2025Aug 2025—Sep 2025South Lanarkshire7.2
Moorhouse (Eaglesham)wind farmwind farm47.5refused on appealupdated Jan 2013Apr 2010refused Apr 2012Jan 2013East Renfrewshire7.6
Cornhills Farm, Muttonhole Roadbattery storagebattery storage49.9approved, not builtupdated Mar 2025Mar 2024granted Feb 2025Mar 2025South Lanarkshire7.9
Myres Hillwind farmwind farm1.8operationalupdated Nov 2001May 1999granted Aug 2001Nov 2001East Renfrewshire8.2
Myres Hill Wind Turbine Test Centrewind farmwind farm1application withdrawnupdated Sep 2019Feb 2019—Sep 2019East Renfrewshire8.2
National Wind Turbine Test Sitewind farmwind farm4.7operationalupdated Nov 2009Aug 1999granted Aug 2000Nov 2009East Renfrewshire8.5
Whiteleewind farmwind farm322operationalupdated May 2010Jan 2002granted Apr 2006May 2010East Renfrewshire9.1
Loganswell Farmwind farmwind farm16application withdrawnupdated Sep 2014Apr 2014—Sep 2014East Renfrewshire9.3
Middleton Wind Farmwind farmwind farm12operationalupdated Mar 2015Feb 2008granted Aug 2011Mar 2015East Renfrewshire9.3
Newton Farm, Westburn Roadbattery storagebattery storage40refusedupdated Apr 2026Jul 2025refused Feb 2026Apr 2026South Lanarkshire9.3
Seath Road, Rutherglenbattery storagebattery storage50refusedupdated Apr 2024Sep 2023refused Mar 2024Apr 2024South Lanarkshire9.3
Downiebrae Road, Rutherglenbattery storagebattery storage150approved, not builtupdated Oct 2025Jan 2025granted Sep 2025Oct 2025Glasgow City9.6
Dalmarnock Roadbattery storagebattery storage40approved, not built may be out of dateupdated Mar 2021Sep 2021granted Feb 2022Mar 2021South Lanarkshire9.6
Whitelee Windfarm Extension Phase 1wind farmwind farm108operationalupdated Apr 2013Apr 2008granted May 2009Apr 2013East Renfrewshire9.8
Whitelee Windfarm Extension Phase 3wind farmwind farm12refused on appealupdated Nov 2016Aug 2012refused Oct 2016Nov 2016East Renfrewshire9.8
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagebattery storagebattery storage50approved, not builtupdated Jan 2025Apr 2021granted Jan 2025Jan 2025East Renfrewshire9.9
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagesolar farmsolar farm40approved, not builtupdated Jan 2025Apr 2021granted Jan 2025Jan 2025East Renfrewshire9.9
Smaller schemes under 1 MW, mostly rooftop solar (23)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tennant Avenue College, East Kilbriderooftop solarrooftop solar0.9under constructionupdated Dec 2022Sep 2022granted May 2023Dec 2022South Lanarkshire1.8
Stroud Road East, Kilbriderooftop solarrooftop solar—approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025South Lanarkshire1.9
Police Training And Recruitment Centre, Eaglesham Roadrooftop solarrooftop solar0.4approved, not builtupdated Mar 2023Feb 2023granted Mar 2023Mar 2023South Lanarkshire2.3
Reynolds Building, Scottish Enterprise Technology Park- Solar Panlesrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023South Lanarkshire2.5
Manson Place, Kelvin Industrial Estaterooftop solarrooftop solar0.2approved, not builtupdated Jul 2023Apr 2023granted Jun 2023Jul 2023South Lanarkshire2.6
Sainsburys, Kingsgate Retail Parkrooftop solarrooftop solar—application submitted may be out of dateupdated Sep 2023Aug 2023—Sep 2023South Lanarkshire4.1
Allers Wastewater Treatment Works, Barrie Roadsolar farmsolar farm0.2operationalupdated Feb 2025Feb 2024granted Apr 2024Feb 2025South Lanarkshire5.3
Linn Products, Glasgow Roadsolar farmsolar farm0.5approved, not builtupdated Mar 2025Feb 2025granted Mar 2025Mar 2025East Renfrewshire5.3
Stanley Boulevard, Hamilton Tech Park - Roof Mounted Photovoltaic Panelsrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024South Lanarkshire7.4
International House, Stanley Boulevardrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2023Jun 2023granted Jun 2023Jul 2023South Lanarkshire7.4
Logoch Windfarm, East Kilbridewind turbinewind turbine0.5approved, not builtupdated Jul 2024Aug 2023granted Mar 2024Jul 2024South Lanarkshire7.5
Scottish Fire & Rescue Service, Westburn Drive Solar Array & BESSsolar farmsolar farm0.6approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026South Lanarkshire8.5
Westburn Drive, Cambuslangrooftop solarrooftop solar0.3approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023South Lanarkshire8.6
Glasgow Road, Blantyrerooftop solarrooftop solar0.4approved, not built may be out of dateupdated Feb 2023Nov 2022granted Feb 2023Feb 2023South Lanarkshire8.9
Scottish Fire & Rescue Service, Westburn Drive Solar Array & BESSbattery storagebattery storage—approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Glasgow City8.9
Cunninghame Road, Farm Castle Industrial Estaterooftop solarrooftop solar0.2approved, not built may be out of dateupdated Sep 2022Aug 2022granted Sep 2022Sep 2022South Lanarkshire9.0
Clyde Gateway Trade Park, Dalmarnock Roadbattery storagebattery storage—application submittedMay 2026——South Lanarkshire9.4
David Lloyd Leisure Health Club, Stewarton Roadrooftop solarrooftop solar0.5approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024East Renfrewshire9.4
Clyde Gateway Developments Limited - D2 Grids Demonstrator Projectsolar farmsolar farm—application submitted may be out of dateupdated Feb 2022Dec 2022—Feb 2022South Lanarkshire9.5
Cambuslang Investment Park, Clydesmill Roadrooftop solarrooftop solar0.5approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Glasgow City9.5
Clyde Avenue, Bothwellsolar farmsolar farm0.7approved, not built may be out of dateupdated Apr 2023Oct 2022granted Mar 2023Apr 2023South Lanarkshire9.5
Dalmarnock Wastewater Treatment Worksrooftop solarrooftop solar—approved, not built may be out of dateupdated May 2021Apr 2021granted Jun 2021May 2021Glasgow City9.7
Strathaven Airfieldrooftop solarrooftop solar—operationalupdated Feb 2021Jan 2021granted Mar 2021Feb 2021South Lanarkshire9.8

Distance from the average position of the G75 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm7151069.7
Rooftop solar15113103.9
Wind farm16109230
Wind turbine701120.5
Battery storage162714434

MW in pipeline: pending, approved and under-construction capacity.

How South Lanarkshire decides solar, wind and battery applications

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

All projects in South Lanarkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near G75, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.