Calder Water Community Wind Farm (28 MW)

Calder Water Community Wind Farm is a 28 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 September 2013; the record was last updated on 25 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28 MWwind farm
operationalstatus in REPD
25 March 2015record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
26 August 2009Application submitted
29 November 2011Planning permission granted
1 September 2013Operational

Project details

Technology
wind farm
Capacity
28 MW
Status (REPD)
operational
Record last updated
25 March 2015
Operator or applicant
Community Windpower (Community Wind Power)
Planning authority
South Lanarkshire
Planning application reference
EK/09/0290
Turbines
14
Address (REPD)
Harshaw Hill, Drumclog, Strathaven, Strathclyde. ML10 6QN
Council area (by location)
South Lanarkshire
Time to decision
118 weeks
REPD reference
3688

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Browncastlewind farm30operational2.4
Low Drumclog Farm, Drumclog - 3 Wind Turbineswind farm20approved, not built4.3
Mill Rig Wind Farmwind farm36under construction5.8
Bankend Rig II Wind Farmwind farm10.2approved, not built5.9
Bankend Rig III Wind Farmwind farm66approved, not built5.9
Dungavel House, IRC Muirkirk Road Wind Farmwind farm11.4approved, not built5.9
Whiteleewind farm322operational6.4
Whitelee Windfarm Extension Phase 1wind farm108operational6.4
Whitelee Windfarm Extension Phase 3wind farm12refused on appeal6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6374, -4.2119).