Dungavel House, IRC Muirkirk Road Wind Farm (11.4 MW)

Dungavel House, IRC Muirkirk Road Wind Farm is an 11.4 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 January 2025, not yet built; the record was last updated on 31 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.4 MWwind farm
approved, not builtstatus in REPD
31 October 2025record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
8 August 2022Application submitted
22 January 2025Planning permission granted

Project details

Technology
wind farm
Capacity
11.4 MW
Status (REPD)
approved, not built
Record last updated
31 October 2025
Operator or applicant
Clean Earth Energy Limited
Planning authority
South Lanarkshire
Planning application reference
P/22/1139
Turbines
3
Turbine height
150 m
Address (REPD)
750M Southeast Of Dungavel House IRC Muirkirk Road
Council area (by location)
South Lanarkshire
Time to decision
128 weeks
Name in REPD
Dungavel House, IRC Muirkirk Road - Wind Farm
REPD reference
12041

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bankend Rig III Wind Farmwind farm66approved, not built<0.1
Bankend Rig II Wind Farmwind farm10.2approved, not built1.6
Dungavel Hillwind farm29.9operational2.1
Bankend Rigwind farm14.3operational3.5
Low Drumclog Farm, Drumclog - 3 Wind Turbineswind farm20approved, not built3.7
Mill Rig Wind Farmwind farm36under construction4.0
Calder Water Community Wind Farmwind farm28operational5.9
Kype Muir Wind Farm Extensionwind farm67.2operational6.5
Kype Muir Wind Farmwind farm88.4operational6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6101, -4.1312).