Energy Projects Near You

Kype Muir Wind Farm Extension (67.2 MW)

Kype Muir Wind Farm Extension is a 67.2 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2024; the record was last updated on 4 November 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

67.2 MWwind farm
operationalstatus in REPD
4 November 2024record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
10 October 2014Application submitted
16 September 2016Section 36 consent granted (Scottish Ministers)
1 June 2021Construction started
1 October 2024Operational

Project details

Technology
wind farm
Capacity
67.2 MW
Status (REPD)
operational
Record last updated
4 November 2024
Operator or applicant
Banks Renewables
Planning authority
Scottish Government (S36)
Planning application reference
EC00002083
Turbines
15
Turbine height
200 m
Address (REPD)
approximately 5 km south of the town of Strathaven
Council area (by location)
South Lanarkshire
Time to decision
101 weeks
REPD reference
4628

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Kype Muir Wind Farmwind farm88.4operational<0.1
Wind turbines at Hawkwood Wind Farm Kype Highway Strathavenwind farm33application submitted2.2
Auchrobert Wind Farmwind farm36operational3.4
Dungavel Hillwind farm29.9operational4.7
West Dykes Headwind farm7.6refused5.5
Goodbush Hillwind farm24application withdrawn5.8
Dungavel House, IRC Muirkirk Road Wind Farmwind farm11.4approved, not built6.5
Bankend Rig III Wind Farmwind farm66approved, not built6.5
Nutberrywind farm60application withdrawn6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6327, -4.0361).