Bankend Rig III Wind Farm (66 MW)

Bankend Rig III Wind Farm is a 66 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 November 2025, not yet built; the record was last updated on 8 January 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

66 MWwind farm
approved, not builtstatus in REPD
8 January 2026record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
23 January 2024Application submitted
21 November 2025Section 36 consent granted (Scottish Ministers)
21 November 2030Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
66 MW
Status (REPD)
approved, not built
Record last updated
8 January 2026
Operator or applicant
Wilson Forrest Products Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004516
Turbines
10
Turbine height
250 m
Address (REPD)
Glengavel Reservoir, Dungavel, Strathaven
Council area (by location)
South Lanarkshire
Time to decision
95 weeks
REPD reference
11670

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Dungavel House, IRC Muirkirk Road Wind Farmwind farm11.4approved, not built<0.1
Bankend Rig II Wind Farmwind farm10.2approved, not built1.6
Dungavel Hillwind farm29.9operational2.1
Bankend Rigwind farm14.3operational3.5
Low Drumclog Farm, Drumclog - 3 Wind Turbineswind farm20approved, not built3.7
Mill Rig Wind Farmwind farm36under construction4.0
Calder Water Community Wind Farmwind farm28operational5.9
Kype Muir Wind Farmwind farm88.4operational6.5
Kype Muir Wind Farm Extensionwind farm67.2operational6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6099, -4.1313).