Energy Projects Near You

Bankend Rig II Wind Farm (10.2 MW)

Bankend Rig II Wind Farm is a 10.2 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 June 2025, not yet built; the record was last updated on 31 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.2 MWwind farm
approved, not builtstatus in REPD
31 October 2025record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
23 July 2021Application submitted
10 June 2025Planning permission granted

Project details

Technology
wind farm
Capacity
10.2 MW
Status (REPD)
approved, not built
Record last updated
31 October 2025
Operator or applicant
Wilson Renewables II Llp
Planning authority
South Lanarkshire
Planning application reference
P/21/1385
Turbines
3
Turbine height
250 m
Address (REPD)
Bankend Rig II Wind Farm, Drumclog, Strathaven
Council area (by location)
South Lanarkshire
Time to decision
203 weeks
REPD reference
9459

Earlier applications for this site

ApplicationMWSubmittedOutcome
Bankend Wind Farm (extension) EK/15/021710.211 June 2015replaced by a revised application
Bankend Rig II Wind Farm EK/15/021710.29 July 2015replaced by a revised application

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bankend Rig III Wind Farmwind farm66approved, not built1.6
Dungavel House, IRC Muirkirk Road Wind Farmwind farm11.4approved, not built1.6
Bankend Rigwind farm14.3operational2.4
Mill Rig Wind Farmwind farm36under construction2.5
Dungavel Hillwind farm29.9operational3.3
Low Drumclog Farm, Drumclog - 3 Wind Turbineswind farm20approved, not built4.8
Calder Water Community Wind Farmwind farm28operational5.9
West Browncastlewind farm30operational7.7
Kype Muir Wind Farm Extensionwind farm67.2operational7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5988, -4.1472).