Energy Projects Near You

Biggar Road, Cleland (30 MW battery storage)

Biggar Road, Cleland is a 30 MW battery storage project in North Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 March 2025, not yet built; the record was last updated on 18 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
approved, not builtstatus in REPD
18 March 2025record last updated
North Lanarkshirecouncil area

Planning timeline

DateStage
20 August 2024Application submitted
12 March 2025Planning permission granted
12 March 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
18 March 2025
Operator or applicant
Starlight Energy SPV 1 Limited
Planning authority
North Lanarkshire
Planning application reference
24/00810/FUL
Address (REPD)
E/O Biggar Road, Cleland., Motherwell
Council area (by location)
North Lanarkshire
Time to decision
29 weeks
Name in REPD
Biggar Road, Cleland - Battery Energy Storage System
REPD reference
17064

Who decides

ApplicationsNorth LanarkshireUK
Decided applications (solar, wind, battery)3810,236
Refused9 (24%)19%
Solar refused0 of 1412%
Onshore wind refused8 of 2045%
Battery storage refused1 of 416%
Median time from submission to decision34.4 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newarthill Energy Parkbattery storage300approved, not built0.6
North Lanrigg Energy Storagebattery storage200approved, not built1.3
Salsburghwind farm24application withdrawn3.6
Fernishaw Solar Farm & Battery Energy Storage Facilitysolar farm75approved, not built3.7
Hartwoodwind farm30application withdrawn4.7
Locks Street, Coatdyke Battery Energy Storage Systemsbattery storage45application submitted5.6
Hartwood Windfarmwind farm21permission expired6.1
Bracco / Black Hillwind farm72.5application withdrawn6.2
Wishaw Battery Storage Facilitybattery storage50operational6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8276, -3.9338).