Solar, wind and battery projects near Airdrie (ML6)
37 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ML6 (North Lanarkshire): 8 are waiting for a planning decision, 17 approved but not yet running, 4 operational. The largest live scheme is Newarthill Energy Park (300 MW battery storage, approved on 4 February 2025, not yet built), 4.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ML6
Projects of 1 MW and more (29)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Wester Moffat Farm, Towers Roadsolar farm | solar farm | 2 | approved, not builtupdated Mar 2026 | Oct 2025 | granted Jan 2026 | Mar 2026 | North Lanarkshire | 1.1 |
| Dalmacoulter Landfill, Dalmacoulter Road Solar Farmsolar farm | solar farm | 1 | approved, not builtupdated Jun 2026 | Aug 2025 | granted Apr 2026 | Jun 2026 | North Lanarkshire | 1.4 |
| A Bartlett and Sonswind turbine | wind turbine | 1 | approved, not builtupdated Aug 2025 | Nov 2023 | granted Jul 2025 | Aug 2025 | North Lanarkshire | 2.3 |
| Damhead Farmwind turbine | wind turbine | 2.5 | operationalupdated Oct 2014 | May 2007 | granted Jan 2010 | Oct 2014 | North Lanarkshire | 2.3 |
| Locks Street, Coatdyke Battery Energy Storage Systemsbattery storage | battery storage | 45 | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 | North Lanarkshire | 2.8 |
| Burnbank Street, Greenhillbattery storage | battery storage | 30 | approved, not builtupdated Sep 2024 | Feb 2024 | granted Aug 2024 | Sep 2024 | North Lanarkshire | 3.4 |
| Brakes, Edinburgh Roadrooftop solar | rooftop solar | 1.4 | approved, not built may be out of dateupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | North Lanarkshire | 4.3 |
| North Lanrigg Energy Storagebattery storage | battery storage | 200 | approved, not builtupdated Aug 2025 | Jul 2024 | granted Jul 2025 | Aug 2025 | North Lanarkshire | 4.6 |
| Biggar Road, Clelandbattery storage | battery storage | 30 | approved, not builtupdated Mar 2025 | Aug 2024 | granted Mar 2025 | Mar 2025 | North Lanarkshire | 4.8 |
| Greengairs East Wind Farmwind farm | wind farm | 24 | operationalupdated Sep 2023 | Jun 2012 | granted Feb 2019 | Sep 2023 | North Lanarkshire | 4.8 |
| Greengairs Wind Farmwind farm | wind farm | 17.5 | permission expiredupdated Sep 2020 | Feb 2007 | granted Aug 2008 | Sep 2020 | North Lanarkshire | 4.8 |
| Newarthill Energy Parkbattery storage | battery storage | 300 | approved, not builtupdated Aug 2025 | Nov 2023 | granted Feb 2025 | Aug 2025 | North Lanarkshire | 4.9 |
| Brew Dog Brewery, Condor Glenrooftop solar | rooftop solar | 1.3 | approved, not built may be out of dateupdated May 2023 | Apr 2023 | granted May 2023 | May 2023 | North Lanarkshire | 5.2 |
| Newhouse, Biggar Road -Solar Arraysolar farm | solar farm | 3.5 | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | North Lanarkshire | 5.5 |
| Bracco / Black Hillwind farm | wind farm | 72.5 | application withdrawnupdated Apr 2008 | — | — | Apr 2008 | North Lanarkshire | 6.1 |
| Greendykesidewind farm | wind farm | 4 | operationalupdated Oct 2009 | Sep 2004 | granted May 2005 | Oct 2009 | North Lanarkshire | 6.1 |
| Salsburghwind farm | wind farm | 24 | application withdrawnupdated Jul 2009 | — | — | Jul 2009 | North Lanarkshire | 6.5 |
| Glenhove Pumping Station, Glenhove Roadbattery storage | battery storage | 3.1 | application submitted | May 2026 | — | — | North Lanarkshire | 6.8 |
| Glenhove Pumping Station, Glenhove Roadsolar farm | solar farm | 1.9 | application submitted | May 2026 | — | — | North Lanarkshire | 6.8 |
| Birniehillwind farm | wind farm | 4.5 | refusedupdated Nov 2012 | Jul 2007 | refused Oct 2012 | Nov 2012 | North Lanarkshire | 6.9 |
| Auchinlea Landfill Site, Carlisle Roadsolar farm | solar farm | 2 | application submittedupdated Nov 2025 | Oct 2025 | — | Nov 2025 | North Lanarkshire | 7.3 |
| Nether braco Farmwind farm | wind farm | 21 | application withdrawnupdated Dec 2011 | Mar 2008 | — | Dec 2011 | North Lanarkshire | 7.4 |
| Fernishaw Solar Farm & Battery Energy Storage Facilitysolar farm | solar farm | 75 | approved, not builtupdated Feb 2026 | Dec 2023 | granted Jul 2025 | Feb 2026 | North Lanarkshire | 8.0 |
| Fernishaw Solar Farm & Battery Energy Storage Facilitybattery storage | battery storage | 25 | approved, not builtupdated Oct 2025 | Dec 2023 | granted Jul 2025 | Oct 2025 | North Lanarkshire | 8.0 |
| Hartwoodwind farm | wind farm | 30 | application withdrawnupdated Nov 2013 | Jun 2006 | — | Nov 2013 | North Lanarkshire | 8.5 |
| Dewshill Wind Farmwind farm | wind farm | 9 | approved, not builtupdated Feb 2026 | Apr 2023 | granted Jun 2024 | Feb 2026 | North Lanarkshire | 8.6 |
| Forrestfield Wind Farmwind farm | wind farm | 13.2 | application submitted may be out of dateupdated Aug 2015 | Jul 2015 | — | Aug 2015 | North Lanarkshire | 9.0 |
| Greenhill Farmwind turbine | wind turbine | 2 | application withdrawnupdated Oct 2017 | Jun 2017 | — | Oct 2017 | Falkirk | 9.2 |
| Hartwood Windfarmwind farm | wind farm | 21 | permission expiredupdated Apr 2020 | Aug 2014 | granted Nov 2017 | Apr 2020 | North Lanarkshire | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Henry Colbeck Officerooftop solar | rooftop solar | 0.2 | operationalupdated Oct 2019 | Apr 2019 | granted May 2019 | Oct 2019 | North Lanarkshire | 3.6 |
| Newhouse, Biggar Roadbattery storage | battery storage | — | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | North Lanarkshire | 5.3 |
| Duart House, Finch Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | North Lanarkshire | 5.9 |
| Avondale House, Phoenix Crescentrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | North Lanarkshire | 6.2 |
| Hollywood Bowl Showcase Leisure Park, Barrbridge Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Aug 2022 | granted Aug 2022 | Nov 2022 | North Lanarkshire | 6.8 |
| Greens Road, Blairlinnrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2024 | Apr 2024 | granted May 2024 | May 2024 | North Lanarkshire | 7.1 |
| Tannochside Drive, Tannochside Parkrooftop solar | rooftop solar | — | approved, not builtupdated Nov 2022 | Oct 2022 | granted Nov 2022 | Nov 2022 | North Lanarkshire | 7.5 |
| Forrest Road, Salsburgh - 2 Wind Turbineswind farm | wind farm | — | application submitted may be out of dateupdated May 2023 | Apr 2023 | — | May 2023 | North Lanarkshire | 8.3 |
Distance from the average position of the ML6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 6 | 3 | 3 | 0 | 0 | 85.4 |
| Rooftop solar | 8 | 0 | 7 | 1 | 0 | 3.6 |
| Wind farm | 12 | 2 | 1 | 2 | 1 | 22.2 |
| Wind turbine | 3 | 0 | 1 | 1 | 0 | 1 |
| Battery storage | 8 | 3 | 5 | 0 | 0 | 633 |
MW in pipeline: pending, approved and under-construction capacity.
How North Lanarkshire decides solar, wind and battery applications
| Applications | North Lanarkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 38 | 10,236 |
| Refused | 9 (24%) | 19% |
| Solar refused | 0 of 14 | 12% |
| Onshore wind refused | 8 of 20 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 34.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 2 | — |
All projects in North Lanarkshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ML6, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.