Dewshill Wind Farm (9 MW)

Dewshill Wind Farm is a 9 MW wind farm project in North Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 June 2024, not yet built; the record was last updated on 10 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWwind farm
approved, not builtstatus in REPD
10 February 2026record last updated
North Lanarkshirecouncil area

Planning timeline

DateStage
26 April 2023Application submitted
19 June 2024Planning permission granted
19 June 2027Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
9 MW
Status (REPD)
approved, not built
Record last updated
10 February 2026
Operator or applicant
Wind Estate (UK) Ltd
Planning authority
North Lanarkshire
Planning application reference
23/00379/FUL
Turbines
2
Turbine height
200 m
Address (REPD)
Forrest Road Salsburgh
Council area (by location)
North Lanarkshire
Time to decision
60 weeks
Contracts for Difference
AR7a
REPD reference
15125

Earlier applications for this site

ApplicationMWSubmittedOutcome
Forrest Road, Salsburgh Wind Farm 22/00324/FUL12.618 March 2022replaced by a revised application

Who decides

ApplicationsNorth LanarkshireUK
Decided applications (solar, wind, battery)3810,236
Refused9 (24%)19%
Solar refused0 of 1412%
Onshore wind refused8 of 2045%
Battery storage refused1 of 416%
Median time from submission to decision34.4 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Benhar Road, Eastfield, Harthillwind farm20application submitted3.0
Bracco / Black Hillwind farm72.5application withdrawn3.0
Forrestfield Wind Farmwind farm13.2application submitted3.1
Brownhill Farmwind farm8.4under construction3.4
Salsburghwind farm24application withdrawn3.6
Shotts wind farmwind farm18refused on appeal3.8
Nether braco Farmwind farm21application withdrawn3.9
Benhar Windfarmwind farm15refused on appeal4.0
West Benhar wind farmwind farm27.2operational4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8498, -3.8279).