Benhar Windfarm (15 MW)

Benhar Windfarm is a 15 MW wind farm project in North Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 3 July 2014; the record was last updated on 30 July 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
refused on appealstatus in REPD
30 July 2014record last updated
North Lanarkshirecouncil area

Planning timeline

DateStage
29 March 2013Application submitted
25 November 2013Refused by the planning authority
3 July 2014Appeal refused

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
refused on appeal
Record last updated
30 July 2014
Operator or applicant
Eneco
Planning authority
North Lanarkshire
Planning application reference
13/00501/FUL
Turbines
5
Address (REPD)
Benhar Windfarm Land South Of West Benhar Road Eastfield Harthill ML7 5TG
Council area (by location)
North Lanarkshire
Time to decision
34 weeks
REPD reference
4214

Who decides

ApplicationsNorth LanarkshireUK
Decided applications (solar, wind, battery)3810,236
Refused9 (24%)19%
Solar refused0 of 1412%
Onshore wind refused8 of 2045%
Battery storage refused1 of 416%
Median time from submission to decision34.4 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Shotts wind farmwind farm18refused on appeal1.0
West Benhar Road, Eastfield, Harthillwind farm20application submitted1.1
Brownhill Farmwind farm8.4under construction1.3
West Benhar wind farmwind farm27.2operational1.5
Torrance Wind Farm Extension 2wind farm26.4refused1.7
Starryshaw Wind Farmwind farm12refused2.2
Torrance Farmwind farm9operational2.7
Torrance Farm Wind Park Extensionwind farm5.7operational3.2
Dewshill Wind Farmwind farm9approved, not built4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8493, -3.7636).