Starryshaw Wind Farm (12 MW)

Starryshaw Wind Farm is a 12 MW wind farm project in North Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 24 December 2014; the record was last updated on 23 July 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
refusedstatus in REPD
23 July 2015record last updated
North Lanarkshirecouncil area

Planning timeline

DateStage
23 April 2013Application submitted
24 December 2014Refused by the planning authority

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
refused
Record last updated
23 July 2015
Operator or applicant
WilloWind Energy Ltd
Planning authority
North Lanarkshire
Planning application reference
13/00669/FUL
Turbines
4
Address (REPD)
Starryshaw Wind Farm Land North Of Starryshaw Farm & Braehead Torbothie Road Stane Shotts North Lanarkshire
Council area (by location)
North Lanarkshire
Time to decision
87 weeks
REPD reference
4257

Who decides

ApplicationsNorth LanarkshireUK
Decided applications (solar, wind, battery)3810,236
Refused9 (24%)19%
Solar refused0 of 1412%
Onshore wind refused8 of 2045%
Battery storage refused1 of 416%
Median time from submission to decision34.4 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Benhar wind farmwind farm27.2operational0.8
Shotts wind farmwind farm18refused on appeal1.4
Brownhill Farmwind farm8.4under construction1.6
Benhar Windfarmwind farm15refused on appeal2.2
West Benhar Road, Eastfield, Harthillwind farm20application submitted2.5
Torrance Wind Farm Extension 2wind farm26.4refused3.6
Damside Wind Farmwind farm20refused4.5
Torrance Farmwind farm9operational4.7
Gladsmuir Hills Wind Farmwind farm41approved, not built4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8301, -3.7573).