Energy Projects Near You

Damside Wind Farm (20 MW)

Damside Wind Farm is a 20 MW wind farm project in North Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 7 March 2013; the record was last updated on 16 May 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWwind farm
refusedstatus in REPD
16 May 2013record last updated
North Lanarkshirecouncil area

Planning timeline

DateStage
20 July 2012Application submitted
7 March 2013Refused by the planning authority

Project details

Technology
wind farm
Capacity
20 MW
Status (REPD)
refused
Record last updated
16 May 2013
Operator or applicant
Damside Wind Farm Ltd
Planning authority
North Lanarkshire
Planning application reference
12/00808/FUL
Turbines
8
Address (REPD)
Barnhill Farm, Farm Dura Road, Allanton, Shotts, Lanarkshire
Council area (by location)
North Lanarkshire
Time to decision
33 weeks
REPD reference
2792

Who decides

ApplicationsNorth LanarkshireUK
Decided applications (solar, wind, battery)3810,236
Refused9 (24%)19%
Solar refused0 of 1412%
Onshore wind refused8 of 2045%
Battery storage refused1 of 416%
Median time from submission to decision34.4 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hartwood Windfarmwind farm21permission expired3.7
Black Law Extension - 1awind farm48.4operational3.9
Black Lawwind farm124operational3.9
Black Law Extension - 1bwind farm15operational3.9
Watsonhead Wind Farmwind farm8.4operational4.0
Starryshaw Wind Farmwind farm12refused4.5
Gladsmuir Hills Wind Farmwind farm41approved, not built4.8
West Benhar wind farmwind farm27.2operational5.0
Hartwoodwind farm30application withdrawn5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7939, -3.79).