Gladsmuir Hills Wind Farm (41 MW)

Gladsmuir Hills Wind Farm is a 41 MW wind farm project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 October 2025, not yet built; the record was last updated on 17 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

41 MWwind farm
approved, not builtstatus in REPD
17 June 2026record last updated
West Lothiancouncil area

Planning timeline

DateStage
25 August 2022Application submitted
13 October 2025Planning permission granted
13 October 2030Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
41 MW
Status (REPD)
approved, not built
Record last updated
17 June 2026
Operator or applicant
Wind Estate (UK) Ltd
Planning authority
West Lothian
Planning application reference
0706/FUL/22
Turbines
6
Turbine height
180 m
Address (REPD)
Gladsmuir Hills Approximately 1km South Of Fauldhouse
Council area (by location)
West Lothian
Time to decision
164 weeks
Name in REPD
Gladsmuir Hills - Wind Farm
REPD reference
10585

Who decides

ApplicationsWest LothianUK
Decided applications (solar, wind, battery)4110,236
Refused5 (12%)19%
Solar refused1 of 1712%
Onshore wind refused4 of 1545%
Battery storage refused0 of 916%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tormywheel Wind Farm Extensionwind farm5approved, not built2.1
Tormywheelwind farm30.8operational2.9
Heathland Wind Farmwind farm80approved, not built3.8
Black Law Extension - 1bwind farm15operational4.6
Black Law Extension - 1awind farm48.4operational4.6
Black Lawwind farm124operational4.6
Damside Wind Farmwind farm20refused4.8
Starryshaw Wind Farmwind farm12refused4.9
West Benhar wind farmwind farm27.2operational5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7934, -3.7135).