Tormywheel (30.8 MW wind farm)

Tormywheel is a 30.8 MW wind farm project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 March 2017; the record was last updated on 31 October 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30.8 MWwind farm
operationalstatus in REPD
31 October 2017record last updated
West Lothiancouncil area

Planning timeline

DateStage
4 February 2005Application submitted
7 June 2007Planning permission granted
7 December 2015Construction started
17 March 2017Operational

Project details

Technology
wind farm
Capacity
30.8 MW
Status (REPD)
operational
Record last updated
31 October 2017
Operator or applicant
BlackRock (formerly Muirhall Energy)
Planning authority
West Lothian
Planning application reference
0551/FUL/11
Turbines
15
Turbine height
111 m
Address (REPD)
Fauldhouse
Council area (by location)
West Lothian
Time to decision
122 weeks
REPD reference
4263

Who decides

ApplicationsWest LothianUK
Decided applications (solar, wind, battery)4110,236
Refused5 (12%)19%
Solar refused1 of 1712%
Onshore wind refused4 of 1545%
Battery storage refused0 of 916%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tormywheel Wind Farm Extensionwind farm5approved, not built0.8
Heathland Wind Farmwind farm80approved, not built1.8
Gladsmuir Hills Wind Farmwind farm41approved, not built2.9
Longhill Burn Wind Farmwind farm45.6under construction2.9
PATES HILL WIND FARM Extensionwind farm6application withdrawn3.6
Pates Hillwind farm14operational4.0
Woolfords Farm - Onshore Wind Turbineswind farm19.8approved, not built4.1
Starryshaw Wind Farmwind farm12refused6.0
Crofthill Wind Farmwind farm17refused6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8048, -3.6721).