Pates Hill (14 MW wind farm)

Pates Hill is a 14 MW wind farm project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 January 2010; the record was last updated on 6 April 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14 MWwind farm
operationalstatus in REPD
6 April 2010record last updated
West Lothiancouncil area

Planning timeline

DateStage
21 July 2005Application submitted
1 June 2006Planning permission granted
1 June 2009Construction started
20 January 2010Operational

Project details

Technology
wind farm
Capacity
14 MW
Status (REPD)
operational
Record last updated
6 April 2010
Operator or applicant
Your Energy
Planning authority
West Lothian
Planning application reference
0653/FUL/07
Turbines
7
Address (REPD)
West Calder Lothian, EH55
Council area (by location)
West Lothian
Time to decision
45 weeks
REPD reference
3232

Who decides

ApplicationsWest LothianUK
Decided applications (solar, wind, battery)4110,236
Refused5 (12%)19%
Solar refused1 of 1712%
Onshore wind refused4 of 1545%
Battery storage refused0 of 916%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
PATES HILL WIND FARM Extensionwind farm6application withdrawn1.1
Longhill Burn Wind Farmwind farm45.6under construction1.1
Woolfords Farm - Onshore Wind Turbineswind farm19.8approved, not built1.7
Pearie Law 2wind farm14.4approved, not built2.4
Pearie Law Wind Farmwind farm19.2operational3.1
Heathland Wind Farmwind farm80approved, not built3.7
Tormywheelwind farm30.8operational4.0
Tormywheel Wind Farm Extensionwind farm5approved, not built4.8
Harburnhead Wind Farmwind farm51.7operational5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8164, -3.6113).