Harburnhead Wind Farm (51.7 MW)

Harburnhead Wind Farm is a 51.7 MW wind farm project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2016; the record was last updated on 4 June 2018. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

51.7 MWwind farm
operationalstatus in REPD
4 June 2018record last updated
West Lothiancouncil area

Planning timeline

DateStage
20 December 2011Application submitted
9 July 2014Section 36 consent granted (Scottish Ministers)
4 February 2016Construction started
1 December 2016Operational

Project details

Technology
wind farm
Capacity
51.7 MW
Status (REPD)
operational
Record last updated
4 June 2018
Operator or applicant
Gresham House
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
22
Turbine height
126 m
Address (REPD)
West Calder, West Lothian
Council area (by location)
West Lothian
Time to decision
133 weeks
REPD reference
4225

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Camilty Plantation Wind Farmwind farm25.8approved, not built1.8
Pearie Law Wind Farmwind farm19.2operational2.3
Fauch Hillwind farm48refused on appeal2.3
Pearie Law 2wind farm14.4approved, not built3.6
Harrow's Lawwind farm39refused on appeal4.6
Fauch Hill Wind Farmwind farm69refused4.7
Woolfords Farm - Onshore Wind Turbineswind farm19.8approved, not built4.7
Pates Hillwind farm14operational5.0
PATES HILL WIND FARM Extensionwind farm6application withdrawn5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8087, -3.5322).