Harrow's Law (39 MW wind farm)

Harrow's Law is a 39 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 23 May 2012; the record was last updated on 14 August 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

39 MWwind farm
refused on appealstatus in REPD
14 August 2012record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
5 March 2010Application submitted
27 June 2011Refused by the planning authority
23 May 2012Appeal refused

Project details

Technology
wind farm
Capacity
39 MW
Status (REPD)
refused on appeal
Record last updated
14 August 2012
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
South Lanarkshire
Planning application reference
CL/10/0095
Turbines
17
Address (REPD)
Harrows Law Dunsyre
Council area (by location)
South Lanarkshire
Time to decision
68 weeks
REPD reference
2725

Earlier applications for this site

ApplicationMWSubmittedOutcome
Harrow's Law11111 March 2010withdrawn 28 April 2010

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Muirhallwind farm12.3operational3.6
Fauch Hillwind farm48refused on appeal4.4
Harburnhead Wind Farmwind farm51.7operational4.6
Muirhall Southwind farm8.3operational4.9
Muirhall Extensionwind farm6.8operational4.9
Fauch Hill Wind Farmwind farm69refused5.0
Camilty Plantation Wind Farmwind farm25.8approved, not built5.8
Crofthill Wind Farmwind farm17refused6.1
Woolfords Farm - Onshore Wind Turbineswind farm19.8approved, not built6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7671, -3.5285).