Harrow's Law (39 MW wind farm)
Harrow's Law is a 39 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 23 May 2012; the record was last updated on 14 August 2012.
39 MWwind farm
refused on appealstatus in REPD
14 August 2012record last updated
South Lanarkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 5 March 2010 | Application submitted |
| 27 June 2011 | Refused by the planning authority |
| 23 May 2012 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 39 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 14 August 2012
- Operator or applicant
- Scottish and Southern Energy (SSE)
- Planning authority
- South Lanarkshire
- Planning application reference
- CL/10/0095
- Turbines
- 17
- Address (REPD)
- Harrows Law Dunsyre
- Council area (by location)
- South Lanarkshire
- Time to decision
- 68 weeks
- REPD reference
- 2725
Earlier applications for this site
| Application | MW | Submitted | Outcome |
|---|---|---|---|
| Harrow's Law | 111 | 11 March 2010 | withdrawn 28 April 2010 |
Who decides
| Applications | South Lanarkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 89 | 10,236 |
| Refused | 30 (34%) | 19% |
| Solar refused | 2 of 20 | 12% |
| Onshore wind refused | 21 of 56 | 45% |
| Battery storage refused | 7 of 13 | 16% |
| Median time from submission to decision | 47.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Muirhall | wind farm | 12.3 | operational | 3.6 |
| Fauch Hill | wind farm | 48 | refused on appeal | 4.4 |
| Harburnhead Wind Farm | wind farm | 51.7 | operational | 4.6 |
| Muirhall South | wind farm | 8.3 | operational | 4.9 |
| Muirhall Extension | wind farm | 6.8 | operational | 4.9 |
| Fauch Hill Wind Farm | wind farm | 69 | refused | 5.0 |
| Camilty Plantation Wind Farm | wind farm | 25.8 | approved, not built | 5.8 |
| Crofthill Wind Farm | wind farm | 17 | refused | 6.1 |
| Woolfords Farm - Onshore Wind Turbines | wind farm | 19.8 | approved, not built | 6.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7671, -3.5285).