Energy Projects Near You

Muirhall South (8.3 MW wind farm)

Muirhall South is an 8.3 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 March 2016; the record was last updated on 17 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.3 MWwind farm
operationalstatus in REPD
17 March 2016record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
18 March 2014Application submitted
7 November 2014Refused by the planning authority
22 December 2014Appeal lodged
10 July 2015Planning permission granted
10 July 2015Appeal allowed
21 January 2016Construction started
17 March 2016Operational

Project details

Technology
wind farm
Capacity
8.3 MW
Status (REPD)
operational
Record last updated
17 March 2016
Operator or applicant
Muirhall Energy
Planning authority
South Lanarkshire
Planning application reference
CL/14/0113
Appeal reference
PPA-380-2050
Turbines
3
Turbine height
147 m
Address (REPD)
Stellashaw Moss, South Lanarkshire
Council area (by location)
South Lanarkshire
Time to decision
68 weeks
REPD reference
4281

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Muirhall Extensionwind farm6.8operational<0.1
Crofthill Wind Farmwind farm17refused1.2
Muirhallwind farm12.3operational1.6
Fordmouthsolar farm5refused on appeal2.3
Calla Wind Farmwind farm18refused4.0
Woolfords Farm - Onshore Wind Turbineswind farm19.8approved, not built4.7
Heathland Wind Farmwind farm80approved, not built4.8
Harrow's Lawwind farm39refused on appeal4.9
PATES HILL WIND FARM Extensionwind farm6application withdrawn5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7584, -3.6055).