Energy Projects Near You

Calla Wind Farm (18 MW)

Calla Wind Farm is an 18 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 18 December 2013; the record was last updated on 20 February 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
refusedstatus in REPD
20 February 2014record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
6 December 2012Application submitted
18 December 2013Refused by the planning authority

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
refused
Record last updated
20 February 2014
Operator or applicant
Willowind Developments
Planning authority
South Lanarkshire
Planning application reference
CL/12/0535
Turbines
6
Address (REPD)
Carnwath, Lanark, Strathclyde
Council area (by location)
South Lanarkshire
Time to decision
54 weeks
REPD reference
4000

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fordmouthsolar farm5refused on appeal1.9
Crofthill Wind Farmwind farm17refused3.5
Muirhall Extensionwind farm6.8operational4.0
Muirhall Southwind farm8.3operational4.0
Muirhallwind farm12.3operational5.3
Harrow's Lawwind farm39refused on appeal7.5
Heathland Wind Farmwind farm80approved, not built7.9
Hill Rig Community Wind Farmwind farm28refused8.3
Woolfords Farm - Onshore Wind Turbineswind farm19.8approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7236, -3.6208).