Muirhall (12.3 MW wind farm)
Muirhall is a 12.3 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2011; the record was last updated on 16 August 2011.
12.3 MWwind farm
operationalstatus in REPD
16 August 2011record last updated
South Lanarkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 30 March 2005 | Application submitted |
| 10 October 2008 | Planning permission granted |
| 1 January 2011 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 12.3 MW
- Status (REPD)
- operational
- Record last updated
- 16 August 2011
- Operator or applicant
- Lomond Energy
- Planning authority
- South Lanarkshire
- Planning application reference
- CL/05/0209
- Turbines
- 6
- Address (REPD)
- Stellashaw Moss, South Lanarkshire
- Council area (by location)
- South Lanarkshire
- Time to decision
- 184 weeks
- REPD reference
- 4683
Who decides
| Applications | South Lanarkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 89 | 10,236 |
| Refused | 30 (34%) | 19% |
| Solar refused | 2 of 20 | 12% |
| Onshore wind refused | 21 of 56 | 45% |
| Battery storage refused | 7 of 13 | 16% |
| Median time from submission to decision | 47.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Muirhall South | wind farm | 8.3 | operational | 1.6 |
| Muirhall Extension | wind farm | 6.8 | operational | 1.6 |
| Crofthill Wind Farm | wind farm | 17 | refused | 2.7 |
| Harrow's Law | wind farm | 39 | refused on appeal | 3.6 |
| Fordmouth | solar farm | 5 | refused on appeal | 3.8 |
| Woolfords Farm - Onshore Wind Turbines | wind farm | 19.8 | approved, not built | 4.0 |
| PATES HILL WIND FARM Extension | wind farm | 6 | application withdrawn | 4.8 |
| Heathland Wind Farm | wind farm | 80 | approved, not built | 5.1 |
| Calla Wind Farm | wind farm | 18 | refused | 5.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7669, -3.5858).