Crofthill Wind Farm (17 MW)

Crofthill Wind Farm is a 17 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 4 November 2014; the record was last updated on 5 December 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17 MWwind farm
refusedstatus in REPD
5 December 2014record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
21 October 2013Application submitted
4 November 2014Refused by the planning authority

Project details

Technology
wind farm
Capacity
17 MW
Status (REPD)
refused
Record last updated
5 December 2014
Operator or applicant
Banks Renewables
Planning authority
South Lanarkshire
Planning application reference
CL/13/0401
Turbines
5
Address (REPD)
Land at Crofthill, Auchengray
Council area (by location)
South Lanarkshire
Time to decision
54 weeks
REPD reference
4314

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Muirhall Southwind farm8.3operational1.2
Muirhall Extensionwind farm6.8operational1.2
Fordmouthsolar farm5refused on appeal1.6
Muirhallwind farm12.3operational2.7
Calla Wind Farmwind farm18refused3.5
Heathland Wind Farmwind farm80approved, not built4.5
Woolfords Farm - Onshore Wind Turbineswind farm19.8approved, not built5.2
PATES HILL WIND FARM Extensionwind farm6application withdrawn5.8
Harrow's Lawwind farm39refused on appeal6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7554, -3.6235).