Woolfords Farm - Onshore Wind Turbines (19.8 MW)

Woolfords Farm - Onshore Wind Turbines is a 19.8 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 May 2025, not yet built; the record was last updated on 25 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.8 MWwind farm
approved, not builtstatus in REPD
25 March 2026record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
17 January 2022Application submitted
30 May 2025Planning permission granted
30 May 2030Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
19.8 MW
Status (REPD)
approved, not built
Record last updated
25 March 2026
Operator or applicant
Woolffords Wind Energy Limited
Planning authority
South Lanarkshire
Planning application reference
P/22/0031
Turbines
3
Turbine height
180 m
Address (REPD)
940M NW/O Woolfords Farm, C203 From Woolfords To A70 At Carnwath Woolfords West Calder
Council area (by location)
South Lanarkshire
Time to decision
176 weeks
REPD reference
8344

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
PATES HILL WIND FARM Extensionwind farm6application withdrawn0.8
Pates Hillwind farm14operational1.7
Longhill Burn Wind Farmwind farm45.6under construction1.9
Heathland Wind Farmwind farm80approved, not built3.0
Pearie Law 2wind farm14.4approved, not built3.5
Pearie Law Wind Farmwind farm19.2operational3.5
Muirhallwind farm12.3operational4.0
Tormywheelwind farm30.8operational4.1
Muirhall Extensionwind farm6.8operational4.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8009, -3.6067).