Heathland Wind Farm (80 MW)

Heathland Wind Farm is an 80 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 February 2022, not yet built; the record was last updated on 9 February 2022. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

80 MWwind farm
approved, not builtstatus in REPD
9 February 2022record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
25 January 2021Application submitted
9 February 2022Section 36 consent granted (Scottish Ministers)
10 January 2028Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
80 MW
Status (REPD)
approved, not built
Record last updated
9 February 2022
Operator or applicant
EDF Energy Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00002218
Turbines
14
Turbine height
180 m
Address (REPD)
Heathland Plantation, near Forth in South
Council area (by location)
South Lanarkshire
Time to decision
54 weeks
Contracts for Difference
AR6
REPD reference
7587

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Earlier applications for this site

ApplicationMWSubmittedOutcome
Heathland Wind Farm EC0000312457.816 February 2016replaced by a revised application

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Tormywheelwind farm30.8operational1.8
Tormywheel Wind Farm Extensionwind farm5approved, not built2.1
Longhill Burn Wind Farmwind farm45.6under construction2.8
PATES HILL WIND FARM Extensionwind farm6application withdrawn2.9
Woolfords Farm - Onshore Wind Turbineswind farm19.8approved, not built3.0
Pates Hillwind farm14operational3.7
Gladsmuir Hills Wind Farmwind farm41approved, not built3.8
Crofthill Wind Farmwind farm17refused4.5
Muirhall Extensionwind farm6.8operational4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7926, -3.6526).